xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

Section 89

SCHEDULE 4Transitional provisions: Crown application

Part 1The principal Act

Introduction

1This Part applies to a development if—

(a)it is a development for which before the relevant date no planning permission is required,

(b)it is not a development or of a description of development for which planning permission is granted by virtue of a development order, and

(c)before the relevant date proposed development notice had been given to the local planning authority.

2In this Part—

(a)the relevant date is the date of commencement of section 79(1);

(b)proposed development notice is notice of a proposal for development given by the developer in pursuance of arrangements made by the Secretary of State in relation to development by or on behalf of the Crown;

(c)the developer is the Crown or a person acting on behalf of the Crown.

Acceptable development

3(1)This paragraph applies if before the relevant date in pursuance of the arrangements either the local planning authority have or the Secretary of State has given notice to the developer that they or he (as the case may be) find the proposed development acceptable.

(2)The notice must be treated as if it is planning permission granted under Part 3 of the principal Act.

(3)If the notice is subject to conditions the conditions have effect as if they are conditions attached to the planning permission.

4(1)This paragraph applies if before the relevant date the local planning authority have in pursuance of the arrangements kept a register of proposed development notices.

(2)The register must be treated as if it is part of the register kept by them in pursuance of section 69 of the principal Act.

Referred proposals

5(1)This paragraph applies if—

(a)before the relevant date the local planning authority have notified the developer in pursuance of the arrangements that they do not find the development acceptable, and

(b)the matter has been referred to but not decided by the Secretary of State.

(2)This paragraph also applies if—

(a)before the relevant date the local planning authority have notified the developer in pursuance of the arrangements that they find the development acceptable subject to conditions, and

(b)the matter has been referred to but not decided by the Secretary of State.

(3)The Secretary of State must deal with the proposal as if it is an appeal by an applicant for planning permission under section 78 of the principal Act.

Pending proposals

6(1)This paragraph applies if before the relevant date—

(a)proposed development notice has been given, but

(b)the local planning authority have not given notice to the developer as mentioned in paragraph 3 or 5.

(2)The principal Act applies as if the proposal is an application for planning permission duly made under Part 3 of that Act.

Part 2The listed buildings Act

Introduction

7This Part applies to works if—

(a)they are works for which before the relevant date no listed building consent is required, and

(b)before the relevant date proposed works notice had been given to the local planning authority.

8In this Part—

(a)the relevant date is the date of commencement of section 79(1);

(b)proposed works notice is notice of a proposal for works given by the person proposing to carry out the works (the developer) in pursuance of arrangements made by the Secretary of State in relation to development by or on behalf of the Crown;

(c)the developer is the Crown or a person acting on behalf of the Crown.

Acceptable works

9(1)This paragraph applies if before the relevant date in pursuance of the arrangements either the local planning authority have or the Secretary of State has given notice to the developer that they or he (as the case may be) find the proposed works acceptable.

(2)The notice must be treated as if it is listed building consent granted under the listed buildings Act.

(3)If the notice is subject to conditions the conditions have effect as if they are conditions attached to the consent.

10(1)This paragraph applies if before the relevant date the local planning authority have in pursuance of the arrangements kept a register of proposed works notices.

(2)The register must be treated as if it is part of the register kept by them in pursuance of the listed buildings Act.

Referred proposals

11(1)This paragraph applies if—

(a)before the relevant date the local planning authority have notified the developer in pursuance of the arrangements that they do not find the works acceptable, and

(b)the matter has been referred to but not decided by the Secretary of State.

(2)This paragraph also applies if—

(a)before the relevant date the local planning authority have notified the developer in pursuance of the arrangements that they find the works acceptable subject to conditions, and

(b)the matter has been referred to but not decided by the Secretary of State.

(3)The Secretary of State must deal with the proposal as if it is an appeal by an applicant for listed building consent under section 20 of the listed buildings Act.

Pending proposals

12(1)This paragraph applies if before the relevant date—

(a)proposed works notice has been given, but

(b)the local planning authority have not given notice to the developer as mentioned in paragraph 9 or 11.

(2)The listed buildings Act applies as if the proposal is an application for listed building consent duly made under that Act.