xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 5U.K.Enterprise management incentives

Part 8U.K.Supplementary provisions

Compliance with time limitsU.K.

53(1)For the purposes of this Part and Part 7 a person [F1(“P”)] is not to be regarded as having failed to do anything required to be done within a particular period of time if—U.K.

(a)[F2P] had a reasonable excuse for not doing it within that period, and

(b)if the excuse ceased to exist, [F2P] did it without unreasonable delay after the excuse ceased to exist.

(2)Where sub-paragraph (1)(b) applies, any further time limit running from the end of the period concerned is instead to run from the time when the thing in question was actually done.

[F3(3)For the purposes of sub-paragraph (1)—

(a)an insufficiency of funds is not a reasonable excuse, unless attributable to events outside P's control, and

(b)where P relies on any other person to do anything, that is not a reasonable excuse unless P took reasonable care to avoid the failure.]