- Latest available (Revised)
- Original (As enacted)
There are outstanding changes not yet made by the legislation.gov.uk editorial team to Channel Tunnel Rail Link Act 1996. Any changes that have already been made by the team appear in the content and are referenced with annotations.![]()
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
This section lists the changes and effects yet to be applied to the whole Act, associated Parts and Chapters where applicable. This includes any insertions of whole new Parts, Chapters or provisions yet to be inserted into this Act. These effects are included in this view as they may be (but won’t necessarily be) relevant to the specific provision that you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
This section lists the commencement orders yet to be applied to the whole Act. These effects are included in this view as they may be (but won’t necessarily be) relevant to the specific provision that you are viewing. Where applicable the commencement orders are listed under two headings, firstly those that bring some part of the Act you are viewing into force and secondly, those that bring into force legislation that affects some part of the legislation you are viewing. If you are viewing a prospective version or there is a prospective version available there may be commencement orders listed here that are relevant to the provision you are viewing.
Commencement Orders bringing legislation that affects this Act into force:
4(1)At any time during the maintenance period relating to any of the scheduled works, the nominated undertaker may—E+W+S+N.I.
(a)enter upon and take possession of any land which is—
(i)within 20 metres from that work, and
(ii)within the limits of deviation for the scheduled works or the limits of land to be acquired or used,
if such possession is reasonably required for the purpose of or in connection with maintaining the work or any ancillary works connected with it, and
(b)construct on the land such temporary works (including the provision of means of access) and structures as may be reasonably so required.
(2)Sub-paragraph (1) above shall not authorise the nominated undertaker to take possession of—
(a)a house,
(b)any other structure which is for the time being occupied, or
(c)a garden belonging to a house.
(3)Not less than 28 days before entering upon and taking possession of land under this paragraph, the nominated undertaker shall give notice to the owners and occupiers of the land of its intention to do so.
(4)The nominated undertaker may only remain in possession of land under this paragraph for so long as may be reasonably required to carry out the maintenance works for which possession of the land was taken.
(5)Before giving up possession of land of which possession has been taken under this paragraph, the nominated undertaker shall restore the land to the reasonable satisfaction of the owners of the land.
(6)The nominated undertaker shall pay compensation to the owners and occupiers of land of which possession is taken under this paragraph for any loss which they may suffer by reason of the exercise in relation to the land of the powers conferred by this paragraph.
(7)Any dispute as to a person’s entitlement to compensation under sub-paragraph (6) above, or as to the amount of the compensation, shall be determined under and in accordance with Part I of the M1Land Compensation Act 1961.
(8)Nothing in this paragraph shall affect any liability to pay compensation under section 10(2) of the M2Compulsory Purchase Act 1965, as applied to the acquisition of land under section 4(1) above, or under any other enactment, otherwise than for loss for which compensation is payable under sub-paragraph (6) above.
(9)In this paragraph—
(a)“the maintenance period”, in relation to any work, means the period beginning with the date on which the work is completed and ending 5 years after the date on which it is brought into general use,
(b)“structure” includes any erection, and
(c)any reference to land within a specified distance of a work includes, in the case of a work under the surface of the ground, a reference to land within the specified distance of any point on the surface below which the work is situated.
Annotations are used to give authority for changes and other effects on the legislation you are viewing and to convey editorial information. They appear at the foot of the relevant provision or under the associated heading. Annotations are categorised by annotation type, such as F-notes for textual amendments and I-notes for commencement information (a full list can be found in the Editorial Practice Guide). Each annotation is identified by a sequential reference number. For F-notes, M-notes and X-notes, the number also appears in bold superscript at the relevant location in the text. All annotations contain links to the affecting legislation.
Modifications etc. (not altering text)
C1Sch. 5 para. 4 applied (with modifications) (19.2.1999) by S.I. 1999/537, art. 13(1), Sch. 3 para. 1-8
Sch. 5 para. 4 applied (with modifications) (22.3.2001) by S.I. 2001/1451, art. 15(1), Sch. 3 paras. 1(e), 3(5)
Marginal Citations
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules only you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: