Channel Tunnel Rail Link Act 1996

1(1)The following provisions of this Part of this Schedule shall, unless otherwise agreed in writing between the nominated undertaker and the Agency, have effect.

(2)In this Part of this Schedule—

  • “the Agency” means the Environment Agency;

  • “construction” includes execution, placing, altering, replacing, relaying and removal;

  • “drainage work” means any watercourse and includes any land which is expected to provide flood storage capacity for any watercourse at intervals not less frequent than—

    (a)

    in the case of land in a rural area, once in 50 years, and

    (b)

    in the case of land in an urban area, once in 100 years,

    or, if more frequent, the appropriate return period for the watercourse for which capacity is provided, and any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage, flood defence or tidal monitoring;

  • “fishery” means any waters containing fish and fish in, or migrating to or from such waters and the spawn, spawning grounds or food of such fish;

  • “plans” includes sections, drawings, specifications and method statements;

  • “specified work” means so much of any permanent or temporary work authorised by Part I of this Act (which includes, for the avoidance of doubt, any dredging and any geotechnical investigations that may be undertaken) as is likely to—

    (a)

    affect any drainage work or the volumetric rate of flow of water in or flowing to or from any drainage work;

    (b)

    affect the flow, purity or quality of water in any watercourse or other surface waters or ground water;

    (c)

    cause obstruction to the free passage of fish or damage to any fishery; or

    (d)

    affect the conservation, distribution or use of water resources; and

  • “watercourse” includes all rivers, streams, ditches, drains, cuts, culverts, dykes, sluices, sewers and passages through which water flows except a public sewer.