SCHEDULE 14Overhead lines: consent

Applications for consent

3(1)An application for consent under this Schedule shall be in writing and shall state—

(a)the length of the electric line to which it relates,

(b)the nominal voltage of that line, and

(c)whether the application to any extent relates to exercise of the power conferred by paragraph 3(1) of Schedule 2 to this Act.

(2)An application for consent under this Schedule shall be accompanied by a map showing—

(a)the land across which the electric line to which it relates is to be installed or kept installed, including details of the route of that line,

(b)the limits of deviation for the scheduled works and the limits of land to be acquired or used, so far as relevant to the application, and

(c)if the application to any extent relates to exercise of the power conferred by paragraph 3(1) of Schedule 2 to this Act, the extent to which it so relates.

4An application for consent under this Schedule shall be supplemented, if the appropriate Ministers so direct in writing, by such additional information as may be specified in the direction.