SCHEDULE 14E+W+S Periodic Review of Mineral Planning Permissions

Time from which conditions determined under this Schedule are to take effectE+W+S

10(1)Where an application has been made under paragraph 6 above in respect of a mining site, each of the mineral permissions relating to the site shall, from the time when the application is finally determined, have effect subject to the conditions to which it is determined under this Schedule that that permission is to be subject.

(2)Sub-paragraph (1) above is without prejudice to paragraph 6(8) above.

Commencement Information

I1Sch. 14 wholly in force at 1.1.1997; Sch. 14 not in force at Royal Assent see s. 125(3); Sch. 14 in force for E.W. at 1.11.1995 by S.I. 1995/2765, art. 2; Sch. 14 in force for S. at 1.1.1997 by S.I. 1996/2857, art. 2