SCHEDULES

SCHEDULE 6E+W+S Roads with special engineering difficulties

Requirement of plan and sectionS

2(1)In a road with special engineering difficulties road works (other than emergency works) involving—S

(a)breaking up or opening the road, or any sewer, drain or tunnel under it, or

(b)tunnelling or boring under the road,

shall not be executed until a plan and section of the works have been settled by agreement between the undertaker and each of the relevant authorities or [F1in the prescribed manner].

(2)For that purpose an undertaker proposing to execute any such works shall submit a plan and section of them to each relevant authority.