- Latest available (Revised)
- Original (As enacted)
There are outstanding changes not yet made by the legislation.gov.uk editorial team to Town and Country Planning Act 1990. Any changes that have already been made by the team appear in the content and are referenced with annotations.![]()
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
This section lists the changes and effects yet to be applied to the whole Act, associated Parts and Chapters where applicable. This includes any insertions of whole new Parts, Chapters or provisions yet to be inserted into this Act. These effects are included in this view as they may be (but won’t necessarily be) relevant to the specific provision that you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
This section lists the commencement orders yet to be applied to the whole Act. These effects are included in this view as they may be (but won’t necessarily be) relevant to the specific provision that you are viewing. Where applicable the commencement orders are listed under two headings, firstly those that bring some part of the Act you are viewing into force and secondly, those that bring into force legislation that affects some part of the legislation you are viewing. If you are viewing a prospective version or there is a prospective version available there may be commencement orders listed here that are relevant to the provision you are viewing.
Commencement Orders bringing legislation that affects this Act into force:
2(1)Where—E+W
(a)planning permission for development consisting of the winning and working of minerals [F1or involving the depositing of refuse or waste materials] is granted, and
(b)the permission is subject to a condition requiring that after [F2the winning and working is completed or the depositing has ceased], the site shall be restored by the use of any or all of the following, namely, subsoil, topsoil and soil-making material,
it may be granted subject also to any such condition as the mineral planning authority think fit requiring that such steps shall be taken as may be necessary to bring land to the required standard for whichever of the following uses is specified in the condition, namely—
(i)use for agriculture;
(ii)use for forestry; or
(iii)use for amenity.
(2)In this Act—
(a)a condition such as is mentioned in paragraph (b) of sub-paragraph (1) is referred to as “a restoration condition”; and
(b)a condition requiring such steps to be taken as are mentioned in that sub-paragraph is referred to as “an aftercare condition”.
(3)An aftercare condition may either—
(a)specify the steps to be taken; or
(b)require that the steps be taken in accordance with a scheme (in this Act referred to as an “aftercare scheme”) approved by the mineral planning authority.
(4)A mineral planning authority may approve an aftercare scheme in the form in which it is submitted to them or may modify it and approve it as modified.
(5)The steps that may be specified in an aftercare condition or an aftercare scheme may consist of planting, cultivating, fertilising, watering, draining or otherwise treating the land.
(6)Where a step is specified in a condition or a scheme, the period during which it is to be taken may also be specified, but no step may be required to be taken after the expiry of the aftercare period.
(7)In sub-paragraph (6) “the aftercare period” means a period of five years from compliance with the restoration condition or such other maximum period after compliance with that condition as may be prescribed; and in respect of any part of a site, the aftercare period shall commence on compliance with the restoration condition in respect of that part.
(8)The power to prescribe maximum periods conferred by sub-paragraph (7) includes power to prescribe maximum periods differing according to the use specified.
(9)In this paragraph “forestry” means the growing of a utilisable crop of timber.
Annotations are used to give authority for changes and other effects on the legislation you are viewing and to convey editorial information. They appear at the foot of the relevant provision or under the associated heading. Annotations are categorised by annotation type, such as F-notes for textual amendments and I-notes for commencement information (a full list can be found in the Editorial Practice Guide). Each annotation is identified by a sequential reference number. For F-notes, M-notes and X-notes, the number also appears in bold superscript at the relevant location in the text. All annotations contain links to the affecting legislation.
Amendments (Textual)
F1Words in Sch. 5 para. 2(1)(a) inserted (25.9.1991) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 21, Sch. 1 para. 14(4)(a) (with s. 84(5)); S.I. 1991/2067, art.3 (subject to art. 4)
F2Words in Sch. 5 para. 2(1)(b) substituted (25.9.1991) by Planning and Compensation Act 1991 (c. 34, SIF 123:1), s. 21, Sch. 1 para. 14(4)(b) (with s. 84(5)); S.I. 1991/2067, art. 3 (subject to art. 4)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules only you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: