27Validity and effect of orders

(1)If the licence holder to whom a final or provisional order relates is aggrieved by the order and desires to question its validity on the ground—

(a)that its making or confirmation was not within the powers of section 25 above; or

(b)that any of the requirements of section 26 above have not been complied with in relation to it,

he may, within 42 days from the date of service on him of a copy of the order, make an application to the court under this section.

(2)On any such application the court may, if satisfied that the making or confirmation of the order was not within those powers or that the interests of the licence holder have been substantially prejudiced by a failure to comply with those requirements, quash the order or any provision of the order.

(3)Except as provided by this section, the validity of a final or provisional order shall not be questioned by any legal proceedings whatever.

(4)The obligation to comply with a final or provisional order shall be a duty owed to any person who may be affected by a contravention of the order.

(5)Where a duty is owed by virtue of subsection (4) above to any person, any breach of the duty which causes that person to sustain loss or damage shall be actionable at the suit or instance of that person.

(6)In any proceedings brought against a licence holder in pursuance of subsection (5) above, it shall be a defence for him to prove that he took all reasonable steps and exercised all due diligence to avoid contravening the order.

(7)Without prejudice to any right which any person may have by virtue of subsection (5) above to bring civil proceedings in respect of any contravention or apprehended contravention of a final or provisional order, compliance with any such order shall be enforceable by civil proceedings by the Director for an injunction or for interdict or for any other appropriate relief.

(8)In this section and section 28 below “the court” means the High Court in relation to England and Wales and the Court of Session in relation to Scotland.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources