Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
This section lists the changes and effects yet to be applied to the whole Act, associated Parts and Chapters where applicable. This includes any insertions of whole new Parts, Chapters or provisions yet to be inserted into this Act. These effects are included in this view as they may be (but won’t necessarily be) relevant to the specific provision that you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
This section lists the commencement orders yet to be applied to the whole Act. These effects are included in this view as they may be (but won’t necessarily be) relevant to the specific provision that you are viewing. Where applicable the commencement orders are listed under two headings, firstly those that bring some part of the Act you are viewing into force and secondly, those that bring into force legislation that affects some part of the legislation you are viewing. If you are viewing a prospective version or there is a prospective version available there may be commencement orders listed here that are relevant to the provision you are viewing.
Commencement Orders bringing legislation that affects this Act into force:
(1)If the licence holder to whom a final or provisional order relates is aggrieved by the order and desires to question its validity on the ground—
(a)that its making or confirmation was not within the powers of section 25 above; or
(b)that any of the requirements of section 26 above have not been complied with in relation to it,
he may, within 42 days from the date of service on him of a copy of the order, make an application to the court under this section.
(2)On any such application the court may, if satisfied that the making or confirmation of the order was not within those powers or that the interests of the licence holder have been substantially prejudiced by a failure to comply with those requirements, quash the order or any provision of the order.
(3)Except as provided by this section, the validity of a final or provisional order shall not be questioned by any legal proceedings whatever.
(4)The obligation to comply with a final or provisional order shall be a duty owed to any person who may be affected by a contravention of the order.
(5)Where a duty is owed by virtue of subsection (4) above to any person, any breach of the duty which causes that person to sustain loss or damage shall be actionable at the suit or instance of that person.
(6)In any proceedings brought against a licence holder in pursuance of subsection (5) above, it shall be a defence for him to prove that he took all reasonable steps and exercised all due diligence to avoid contravening the order.
(7)Without prejudice to any right which any person may have by virtue of subsection (5) above to bring civil proceedings in respect of any contravention or apprehended contravention of a final or provisional order, compliance with any such order shall be enforceable by civil proceedings by the Director for an injunction or for interdict or for any other appropriate relief.
(8)In this section and section 28 below “the court” means the High Court in relation to England and Wales and the Court of Session in relation to Scotland.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules only you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: