Search Legislation

Acquisition of Land Act 1981

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to Acquisition of Land Act 1981. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Schedule 2 Part III:

  • Sch. 2 Pt. 3 incorporated (with modifications) by S.I. 2015/680 art. 19
  • Sch. 2 Pt. 2 3 incorporated (with modifications) by S.I. 2020/1297 art. 20 (This amendment not applied to legislation.gov.uk. S.I. 2020/1297 was withdrawn following a request from the Department of Transport dated 9th August 2021 which followed the decision of the High Court of Justice to quash this Order in the judgement dated 2nd August 2021 (High Court of Justice — Planning Court — The Queen (on the application of Save Stonehenge World Heritage Site) v. Secretary of State for Transport — Case No. CO/4844/2020))
  • Sch. 2 Pt. 3 incorporated (with modifications) by S.I. 2021/51 art. 24 (This amendment not applied to legislation.gov.uk. S.I. 2021/51 removed from the website by request from the Department of Transport dated 12th July 2021 which followed the decision of the High Court of Justice to quash these Regulations in the judgement dated 8th July 2021 (High Court of Justice — Planning Court — The Queen (on the application of Mair Bain) v. Secretary of State for Transport — Case No. CO/642/2021).)
  • Sch. 2 Pt. 2 3 incorporated (with modifications) by S.I. 2024/230 art. 47
  • Sch. 2 Pt. 2 3 incorporated (with modifications) by S.I. 2024/360 art. 20
  • Sch. 2 Pt. 2 3 incorporated (with modifications) by S.I. 2024/393 art. 23
  • Sch. 2 Pt. 2 3 incorporated (with modifications) by S.I. 2024/436 art. 28

Changes and effects yet to be applied to the whole Act associated Parts and Chapters:

Whole provisions yet to be inserted into this Act (including any effects on those provisions):

Part IIIE+W

Modifications etc. (not altering text)

C2Sch. 2 Pts. 2, 3 applied (with modifications) by Dartford-Thurrock Crossing Act 1988 (c. 20, SIF 59), s. 2(5), Sch. 2 Pt. 2 para. 4(1)

Sch. 2 Pt. 3 applied (with modifications) (28.7.1998) by 1998 c. iv, s. 7(1)(2)(with s. 41)

Sch. 2 Pts. 2, 3 applied (with modifications) (3.6.1999) by S.I. 1999/1555, art. 9

Sch. 2 Pt. 3 applied (with modifications) (E.) (29.3.2001) by S.I. 2001/1347, art. 36(1) (with arts. 15, 37, 38(2))

Sch. 2 Pt. 3 applied (with modifications) (E.) (29.3.2001) by S.I. 2001/1348, art. 12(1)

C3Sch. 2 Pt. 3 modified (18.12.1996) by 1996 c. 61, s. 4, Sch. 4 Pt. 3 para. 13

C4Sch. 2 Pt. 3 applied (with modifications) (12.8.2002) by The Channel Tunnel Rail Link (Thames Tunnel Approach) Order 2002 (S.I. 2002/1943), art. 6(2)

Sch. 2 Pt. 3 applied (with modifications) (14.3.2002) by The Chester Guided Busway Order 2002 (S.I. 2002/412), art. 39(1) (with art. 38)

C6Sch. 2 Pts. 2, 3 applied (with modifications) (22.7.2005) by The Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (S.I. 2005/1794), arts. 1, 46(1) (with art. 47)

C7Sch. 2 Pt. 3 applied (with modifications) (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 6 para. 17

C8Sch. 2 Pt. 3 applied (with modifications) (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 3 para. 3(5)

C9Sch. 2 Pts. 2, 3 incorporated (with modifications) (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 14 (with art. 30)

C10Sch. 2 Pt. 3 incorporated (with modifications) (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 23

Sch. 2 Pt. 3 incorporated (with modifications) (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 40

C11Sch. 2 Pts. 1-3 applied (with modifications) (2.10.2014) by The Clocaenog Forest Wind Farm Order 2014 (S.I. 2014/2441), arts. 1, 22 (with art. 33)

C12Sch. 2 Pt. 3 incorporated (with modifications) (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 32 (with arts. 30(4), 53)

C14Sch. 2 Pts. 2, 3 incorporated (with modifications) (9.6.2015) by The White Moss Landfill Order 2015 (S.I. 2015/1317), arts. 1, 13 (with art. 5)

C16Sch. 2 Pts. 2, 3 incorporated in part (with modifications) (14.8.2015) by The Hirwaun Generating Station Order 2015 (S.I. 2015/1574), arts. 1, 17(1) (with art. 30)

C17Sch. 2 Pt. 3 incorporated in part (with modifications) (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 14 (with art. 26)

C18Sch. 2 Pts. 2, 3 incorporated (with modifications) (2.2.2016) by The East Midlands Gateway Rail Freight Interchange and Highway Order 2016 (S.I. 2016/17), arts. 1, 27

C19Sch. 2 Pt. 3 incorporated in part (with modifications) (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 20 (with art. 32)

C20Sch. 2 Pts. 2, 3 incorporated in part (with modifications) (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 21 (with art. 39)

C21Sch. 2 Pts. 2, 3 incorporated (with modifications) (1.6.2016) by The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016 (S.I. 2016/547), arts. 1, 21 (with arts. 4, 5(3))

C23Sch. 2 Pts. 2, 3 incorporated (with modifications) (10.8.2016) by The York Potash Harbour Facilities Order 2016 (S.I. 2016/772), arts. 1, 26 (with arts. 35, 36)

C24Sch. 2 Pts. 2, 3 incorporated (with modifications) (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), arts. 1, 37 (with art. 43)

C25Sch. 2 Pts. 2, 3 incorporated in part (with modifications) (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 33

C28Sch. 2 Pt. 3 incorporated (with modifications) (24.8.2017) by The National Grid (Richborough Connection Project) Development Consent Order 2017 (S.I. 2017/817), arts. 1, 19 (with art. 22)

C29Sch. 2 Pts. 2, 3 incorporated (with modifications) (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), arts. 1, 22 (with arts. 4, 37)

C30Sch. 2 Pts. 2, 3 incorporated (with modifications) (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), arts. 1(2), 20

C32Sch. 2 Pt. 3 incorporated (with modifications) (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 19

C33Sch. 2 Pt. 3 incorporated (with modifications) (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), arts. 1, 33

C34Sch. 2 Pt. 3 incorporated in part (with modifications) (30.10.2019) by The Northampton Gateway Rail Freight Interchange Order 2019 (S.I. 2019/1358), arts. 1, 28 (with Sch. 13 Pt. 1 para. 19)

C35Sch. 2 Pt. 3 incorporated (with modifications) (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 24 (with art. 3(1))

C37Sch. 2 Pt. 3 incorporated in part (with modifications) (25.5.2020) by The West Midlands Rail Freight Interchange Order 2020 (S.I. 2020/511), arts. 1, 28(1) (with art. 28(2))

C38Sch. 2 Pt. 3 incorporated (with modifications) (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 25 (with art. 37)

C40Sch. 2 Pt. 3 incorporated (with modifications) (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), arts. 1, 26(b)

C41Sch. 2 Pt. 3 applied (with modifications) (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 7 para. 4(3)(4)

C43Sch. 2 Pt. 3 incorporated (with modifications) (19.2.2021) by The A303 Sparkford to Ilchester Dualling Development Consent Order 2021 (S.I. 2021/125), arts. 1, 24 (with arts. 4, 47)

C44Sch. 2 Pt. 3 incorporated (with modifications) (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), arts. 1, 30 (with arts. 15, 50, Sch. 11 para. 29)

C45Sch. 2 Pts. 2, 3 incorporated (with modifications) (6.6.2022) by The M25 Junction 28 Development Consent Order 2022 (S.I. 2022/573), arts. 1, 26 (with arts. 5, 36)

C47Sch. 2 Pt. 3 incorporated (with modifications) (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 29 (with arts. 62, 76, 87)

C51Sch. 2 Pt. 3 incorporated (with modifications) (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 25 (with art. 4)

C52Sch. 2 Pt. 3 incorporated (with modifications) (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 25 (with arts. 4, 50)

C53Sch. 2 Pt. 3 incorporated in part (with modifications) (18.7.2023) by The Longfield Solar Farm Order 2023 (S.I. 2023/734), arts. 1, 44 (with art. 19)

C57Sch. 2 Pts. 2, 3 incorporated (with modifications) (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 24 (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))

C58Sch. 2 Pts. 2, 3 incorporated (with modifications) (11.10.2023) by The Awel y Môr Offshore Wind Farm Order 2023 (S.I. 2023/1033), arts. 1, 21 (with arts. 36, 37, Sch. 9 para. 14, 44(1), 76, 103)

C60Sch. 2 Pts. 2, 3 incorporated (with modifications) (9.2.2024) by The A12 Chelmsford to A120 Widening Development Consent Order 2024 (S.I. 2024/60), arts. 1, 28 (with arts. 4, 52, Sch. 11 paras. 6, 24, 39(1), 55(1), 84)

C61Sch. 2 Pts. 2, 3 incorporated (with modifications) (11.3.2024) by The Net Zero Teesside Order 2024 (S.I. 2024/174), arts. 1, 36 (with arts. 42, 43, Sch. 12)

3(1)If the owner of any underlying mines or minerals desires to work them, he shall give the acquiring authority notice in writing of his intention to do so 30 days before the commencement of working.E+W

(2)On receipt of the notice the acquiring authority may cause the mines to be inspected by a person appointed by them for the purpose.

(3)Subject to paragraph 4(1) below, if the acquiring authority consider that the working of the underlying mines or minerals is likely to damage the undertaking, and is willing to compensate the owner for all or any part of the mines, the owner shall not work or get them.

(4)If the acquiring authority and the owner do not agree on the amount of compensation the question shall be referred to and determined by the [F1Upper Tribunal].

4(1)If before the expiration of 30 days from the receipt of notice under paragraph 3(1) above the acquiring authority do not state their willingness to treat with the owner for the payment of compensation the owner may work any of the underlying mines for which the acquiring authority has not agreed to pay compensation by proper methods and in the usual manner of working such mines in the district in question.E+W

(2)If any damage or obstruction to the undertaking is caused by improper working of the underlying mines—

(a)the owner of the mines shall forthwith repair or remove the damage or obstruction at his own expense,

(b)the acquiring authority may, without waiting for the owner to perform his duty, or in case of his default, repair or remove the damage or obstruction and recover their expenses from the owner in proceedings in the High Court.

Severed minesE+W

5(1)If underlying mines in which any protected minerals are situated extend on both sides of the undertaking, the owner of the mines may cut and make any communication works through the protected minerals required for the ventilation, drainage and working of the mines.E+W

(2)The communication works shall not exceed the dimensions or sections prescribed by the compulsory purchase order, and where dimensions are not so prescribed, they shall not be more than eight feet high and eight feet wide.

(3)The communication works shall not be cut or made on any part of the undertaking, or so as to injure it or impede its use.

(4)In this paragraph—

(a)protected minerals” means mines, measures or strata the working of which is prevented under paragraph 3(3) above,

(b)communication works” means airways, headings, gateways or water levels.

6(1)If underlying mines extend on both sides of the undertaking, the acquiring authority shall from time to time pay to the owner of the mines (in addition to any compensation under paragraph 3 above) any expenses and losses incurred by him in consequence of—E+W

(a)the severance by the undertaking of the land lying over the mines,

(b)the interruption of continuous working of the mines in consequence of paragraph 3(3) above, and

(c)the mines being worked in such manner and subject to such restrictions as not to prejudice or injure the undertaking,

and for any minerals not purchased by the acquiring authority which cannot be obtained by reason of the making and maintenance of the undertaking.

(2)Any dispute as to the amount payable under this paragraph shall be determined by arbitration.

7(1)Where works carried out under paragraph 5 above cause loss or damage to the owner or occupier of land lying over the mines the acquiring authority shall pay full compensation to him for the loss or damage.E+W

(2)This paragraph shall not apply where the person sustaining the loss or damage is the owner of the mines.

Powers of entryE+W

8(1)For the purpose of ascertaining whether underlying mines have been worked so as to damage the undertaking the acquiring authority may, after giving 24 hours notice in writing—E+W

(a)enter on any land in which the mines are, or are thought to be, being worked, and which is in or near to the land where the undertaking is situated, and

(b)enter the mines and any works connected with the mines.

(2)For the said purpose the acquiring authority may make use of any apparatus or machinery belonging to the owner of the mines, and may use all necessary means for discovering the distance from the undertaking to the parts of the mines which are, or are about to be, worked.

(3)If the owner of the mines refuses to allow a person appointed by the acquiring authority for the purpose to enter the mines or works under this paragraph he shall be liable on summary conviction to a sum not exceeding £50.

Remedial worksE+W

9(1)If it appears that mines have been worked contrary to the provisions of this Schedule, the acquiring authority may give notice to the owner of the mines to construct such works and adopt such means as may be necessary or proper for making safe the undertaking, and preventing injury to it.E+W

(2)If the owner of the mines does not comply with the notice, the acquiring authority may themselves construct the works, and may recover their expenses from the owner by proceedings in the High Court.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources