Town and Country Planning (Minerals) Act 1981

Status:

This is the original version (as it was originally enacted).

22Imposition of aftercare conditions on planning permission

The following section shall be inserted after section 27 of the 1972 Act—

27AAftercare conditions on permission for winning and working of minerals.

(1)Where planning permission for development consisting of the winning and working of minerals is granted subject to a restoration condition, it may be granted subject also to any such aftercare condition as the planning authority think fit.

(2)In this Act—

  • " restoration condition" means a condition requiring that after operations for the winning and working of minerals have been completed, the site shall be restored by the use of any or all of the following, namely, subsoil, topsoil and soil-making material; and

  • " aftercare condition" means a condition requiring that such steps shall be taken as may be necessary to bring land to the required standard for whichever of the following uses is specified in the condition, namely—

    (a)

    use for agriculture ;

    (b)

    use for forestry; or

    (c)

    use for amenity.

(3)An aftercare condition may either—

(a)specify the steps to be taken; or

(b)require that the steps be taken in accordance with a scheme (in this section referred to as an "aftercare scheme") approved by the planning authority.

(4)A planning authority may approve an aftercare scheme in the form in which it is submitted to them or may modify it and approve it as modified.

(5)The steps that may be specified in an aftercare condition or an aftercare scheme may consist of planting, cultivating, fertilising, watering, draining or otherwise treating the land.

(6)Where a step is specified in a condition or a scheme, the period during which it is to be taken may also be specified, but no step may be required to be taken after the expiry of the aftercare period.

(7)In subsection (6) of this section " the aftercare period" means a period of five years from compliance with the restoration condition or such other maximum period after compliance with that condition as may be prescribed; and in respect of any part of a site, the aftercare period shall commence on compliance with the restoration condition in respect of that part.

(8)The power to prescribe maximum periods conferred by subsection (7) of this section includes power to prescribe maximum periods differing according to the use specified.

(9)In a case where—

(a)the use specified is a use for agriculture; and

(b)the land was in use for agriculture at the time of the grant of the planning permission or had previously been used for that purpose and had not at the time of the grant been used for any authorised purpose since its use for agriculture ceased; and

(c)the planning authority is aware of or can readily ascertain the physical characteristics of the land when it was last used for agriculture,

the land is brought to the required standard when its physical characteristics are restored, so far as it is practicable to do so, to what they were when it was last used for agriculture.

(10)In any other case where the use specified is a use for agriculture the land is brought to the required standard when it is reasonably fit for that use.

(11)Where the use specified is a use for forestry, the land is brought to the required standard when it is reasonably fit for that use.

(12)Where the use specified is a use for amenity, the land is brought to the required standard when it is suitable for sustaining trees, shrubs or plants.

(13)Before imposing an aftercare condition in a case where the use specified in the condition is for forestry, the planning authority shall consult the Forestry Commission as to whether it is appropriate to specify that use.

(14)Where after consultations required by subsection (13) of this section the planning authority are satisfied that the use that they ought to specify is a use for forestry, they shall consult the Forestry Commission with regard to whether the steps to be taken should be specified in the aftercare condition or in an aftercare scheme.

(15)The planning authority shall also consult the Forestry Commission—

(a)as to the steps to be specified in an aftercare condition which specifies a use for forestry; and

(b)before approving an aftercare scheme submitted in accordance with an aftercare condition which specifies such a use.

(16)The planning authority shall also, from time to time as they consider expedient, consult the Commission as to whether the steps specified in an aftercare condition or an aftercare scheme are being taken.

(17)On the application of any person with an interest in land in respect of which an aftercare condition has been imposed the planning authority, if they are satisfied that the condition has been complied with, shall issue a certificate to that effect.

(18)A person who has complied with an aftercare condition but who has not himself carried out any operations for the winning and working of minerals in, on or under the land shall be entitled, subject to any condition to the contrary contained in a contract which is enforceable against him by the person who last carried out such operations, to recover from that person any expenses reasonably incurred by him in complying with the aftercare condition.

(19)In this section " authorised " means authorised by planning permission and " forestry" means the growing of a utilisable crop of timber..

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources