SCHEDULE 2E+W+S Storage Authorisation Orders

Part IIE+W+S Procedure for making Orders

Formal application for orderE+W+S

9(1)[F1The applicant]shall at the time of making [F2his application]inform the Minister of the extent to which [F3he has been, or expects]to be, able to acquire by negotiation the land and rights which [F3he must]possess in order to develop and operate the underground gas storage.E+W+S

(2)If the Minister, after consultation with [F1the applicant], is satisfied that a compulsory purchase order will be required to put [F1the applicant]in possession of any such land or right he may, if he thinks fit, give notice to [F1the applicant]that he will not proceed with the application until [F1the applicant][F4has]made such a compulsory purchase order and [F4has]applied to the Minister for the confirmation of the order, and that he will then proceed concurrently with respect to the application under this Schedule and with respect to the application for confirmation of the compulsory purchase order.

(3)Where the Minister gives notice to [F1the applicant]under the last foregoing sub-paragraph, he shall give a like notice to every person on whom a notice was served under paragraph 7(3) of this Schedule and who has duly made an objection to the application which has not been withdrawn.

(4)Where the Minister has given notice to [F1the applicant]under sub-paragraph (2) of this pargraph he shall not (unless he otherwise determines) be required to proceed with the application under this Schedule except in accordance with the notice and the Minister may at any stage decline to proceed with the application if the compulsory purchase order is withdrawn or cannot be proceeded with.