Assumptions as to planning permission

22Assumptions as to planning permission

(1)For the purpose of assessing compensation in respect of any compulsory acquisition, such one or more of the assumptions mentioned in sections 23 and 24 of this Act as are applicable to the relevant land or any part thereof shall be made in ascertaining the value of the relevant interest.

(2)Any planning permission which is to be assumed in accordance with any of the provisions of those sections is in addition to any planning permission which may be in force at the date of service of the notice to treat.

(3)Nothing in those provisions shall be construed as requiring it to be assumed that planning permission would necessarily be refused for any development which is not development for which, in accordance with those provisions, the granting of planning permission is to be assumed; but, in determining whether planning permission for any development could in any particular circumstances reasonably have been expected to be granted in respect of any land, regard shall be had to any contrary opinion expressed in relation to that land in any certificate issued under Part IV of this Act.

(4)For the purposes of any reference in this section, or in section 23 of this Act, to planning permission which is in force on the date of service of the notice to treat, it is immaterial whether the planning permission in question was granted—

(a)unconditionally or subject to conditions, or

(b)in respect of the land in question taken by itself or in respect of an area including that land, or

(c)on an ordinary application or on an outline application or by virtue of a development order,

or is planning permission which, in accordance with any direction or provision given or made by or under any enactment, is deemed to have been granted.

23Assumptions not directly derived from development plans

(1)In a case where—

(a)the relevant interest is to be acquired for purposes which involve the carrying out of proposals of the acquiring authority for development of the relevant land or part thereof, and

(b)on the date of service of the notice to treat there is not in force planning permission for that development,

it shall be assumed that planning permission would be granted, in respect of the relevant land or that part thereof, as the case may be, such as would permit development thereof in accordance with the proposals of the acquiring authority.

(2)For the purposes of paragraph (b) of the preceding subsection, no account shall be taken of any planning permission so granted as not to enure (while the permission remains in force) for the benefit of the land and of all persons for the time being interested therein.

(3)Subject to subsection (4) of this section, it shall be assumed that planning permission would be granted, in respect of the relevant land or any part thereof, for development of any class specified in Schedule 3 to the Town and Country Planning (Scotland) Act 1947 (which relates to development included in the existing use of land).

(4)Notwithstanding anything in subsection (3) of this section—

(a)it shall not by virtue of that subsection be assumed that planning permission would be granted, in respect of the relevant land or any part thereof, for development of any class specified in Part II of the said Schedule 3, if it is development for which planning permission was refused at any time before the date of service of the notice to treat and compensation under section 18 of the said Act of 1947 became payable in respect of that refusal;

(b)where, at any time before the said date, planning permission was granted, in respect of the relevant land or any part thereof, for development of any class specified in the said Part II, but was so granted subject to conditions, and compensation under the said section 18 became payable in respect of the imposition of the conditions, it shall not by virtue of the said subsection (3) be assumed that planning permission for that development, in respect of the relevant land or that part thereof, as the case may be, would be granted otherwise than subject to those conditions;

(c)where, at any time before the said date, an order was made under section 24 of the said Act of 1947, in respect of the relevant land or any part thereof, requiring the removal of any building or the discontinuance of any use, and compensation became payable in respect of that order under section 25 of that Act, it shall not by virtue of the said subsection (3) be assumed that planning permission would be granted, in respect of the relevant land or that part thereof, as the case may be, for the rebuilding of that building or the resumption of that use.

(5)Where a certificate is issued under the provisions of Part IV of this Act, it shall be assumed that any planning permission which, according to the certificate, might reasonably have been expected to be granted in respect of the relevant land or part thereof would be so granted, but, where any conditions are, in accordance with those provisions, specified in the certificate, only subject to those conditions and, if any future time is so specified, only at that time.

24Special assumptions in respect of certain land comprised in development plans

(1)If the relevant land or any part thereof (not being land subject to comprehensive development) consists or forms part of a site defined in the current development plan as the site of proposed development of a description specified in relation thereto in the plan, it shall be assumed that planning permission would be granted for that development.

(2)If the relevant land or any part thereof (not being land subject to comprehensive development) consists or forms part of an area shown in the current development plan as an area allocated primarily for a use specified in the plan in relation to that area, it shall be assumed that planning permission would be granted, in respect of the relevant land or that part thereof, as the case may be, for any development which—

(a)is development for the purposes of that use of the relevant land or that part thereof, and

(b)is development for which planning permission might reasonably have been expected to be granted in respect of the relevant land or that part thereof, as the case may be.

(3)If the relevant land or any part thereof (not being land subject to comprehensive development) consists or forms part of an area shown in the current development plan as an area allocated primarily for a range of two or more uses specified in the plan in relation to the whole of that area, it shall be assumed that planning permission would be granted, in respect of the relevant land or that part thereof, as the case may be, for any development which—

(a)is development for the purposes of a use of the relevant land or that part thereof, being a use falling within that range of uses, and

(b)is development for which planning permission might reasonably have been expected to be granted in respect of the relevant land or that part thereof, as the case may be.

(4)If the relevant land or any part thereof is land subject to comprehensive development, it shall be assumed that planning permission would be granted, in respect of the relevant land or that part thereof, as the case may be, for any development for the purposes of a use of the relevant land or that part thereof falling within the planned range of uses (whether it is the use which, in accordance with the particulars and proposals comprised in the current development plan in relation to the area in question, is indicated in the plan as the proposed use of the relevant land or that part thereof, or is any other use falling within the planned range of uses) being development for which, in the circumstances specified in the next following subsection, planning permission might reasonably have been expected to be granted in respect of the relevant land or that part thereof, as the case may be.

(5)The circumstances referred to in the last preceding subsection are those which would have existed if—

(a)the area in question had not been defined in the current development plan as an area of comprehensive development, and no particulars or proposals relating to any land in that area had been comprised in the plan, and

(b)in a case where, on the date of service of the notice to treat, land in that area has already been developed in the course of the development or redevelopment of the area in accordance with the plan, no land in that area had been so developed on or before that date ;

and in that subsection " the planned range of uses " means the range of uses which, in accordance with the particulars and proposals comprised in the current development plan in relation to the area in question, are indicated in the plan as proposed uses of land in that area.

(6)Where in accordance with any of the preceding subsections it is to be assumed that planning permission would be granted as therein mentioned—

(a)the assumption shall be that planning permission would be so granted subject to such conditions (if any) as, in the circumstances mentioned in the subsection in question, might reasonably be expected to be imposed by the authority granting the permission, and

(b)if, in accordance with any map or statement comprised in the current development plan, it is indicated that any such planning permission would be granted only at a future time, then (without prejudice to the preceding paragraph) the assumption shall be that the planning permission in question would be granted at the time when, in accordance with the indications in the plan, that permission might reasonably be expected to be granted.

(7)Any reference in this section to development for which planning permission might reasonably have been expected to be granted is a reference to development 'for which planning permission might reasonably have been expected to be granted if no part of the relevant land were proposed to be acquired by any authority possessing compulsory purchase powers.

(8)In this section "land subject to comprehensive development " means land which consists or forms part of an area defined in the current development plan as an area of comprehensive development.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources