6(1)In the construction of Work No. 1, the Board may—
(a)deviate from the line or situation thereof shown on the deposited plan to the extent of the limit of deviation; and
(b)subject to subsection (2) below, deviate vertically from the levels shown on the deposited section to any extent not exceeding 1 metre upwards or downwards.