Section 5.
Work No. 1 A weir across the river with movable floodgates, incorporating a fish pass and associated structures, commencing on the northern bank of the river at reference point ST58517205 and terminating on the southern bank of the river at reference point ST58487201;
Work No. 1A An extension of Milne’s Culvert by way of a culvert and outfall into the river commencing in the northern bank of the river at reference point ST58577206 and terminating in the northern bank of the river at reference point ST58487205;
Work No. 2 A reopening of the navigation at the former lock at the western end of Bathurst Basin by the removal of all or part of the existing dam or wall and the installation of new gates and ancillary works for the purposes of excluding flood water from the Floating Harbour and regulating water levels;
Work No. 3 A reopening of the navigation at the former Totterdown Lock by the installation of new gates and ancillary works for the purposes of excluding flood water from the Floating Harbour and regulating water levels;
Work No. 4 An interceptor sewer commencing in Albert Road by a junction with the existing Albert Road sewer at a point 10 metres south of the junction of Albert Road with Victor Street, passing under Albert Road for a distance of 207 metres, then passing in a north-easterly and easterly direction for a distance of 179 metres in land north of Albert Road, then passing in a south-westerly direction for a distance of 52 metres to a point in Albert Road 120 metres east of the junction of that road with Totterdown Bridge, then passing under Albert Road for a distance of 475 metres and terminating by a junction with the existing Albert Road sewer at a point 235 metres north-east of the junction of Albert Crescent with Albert Road;
Work No. 4A A sewer commencing by a junction with Work No. 4 at a point in Albert Road 202 metres east of the junction of that road with Totterdown Bridge, then passing in a north-westerly direction for a distance of 108 metres and terminating in that land at a point 38 metres north of Albert Road;
Work No. 4B A sewer commencing by a junction with Work No. 4 at a point in Albert Road 120 metres east of the junction of that road with Totterdown Bridge, then passing in a south-westerly direction for a distance of 17 metres and terminating by a junction with an existing sewer at a point six metres south of Albert Road.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: