Consents for certain discharges under Article 226

227.—(1) Except in an emergency, no discharge through any pipe the diameter of which exceeds 300 millimetres shall be made under Article 226 except with the consent of each relevant department and of any navigation authority which carries out functions in relation to—

(a)the part of the watercourse where the discharge is made; or

(b)any part of that watercourse which is less than three miles downstream from the place of the discharge.

(2) Where a water undertaker makes an application for a consent for the purposes of this Article—

(a)that application shall be accompanied or supplemented by all such information as a relevant department or the navigation authority may reasonably require; and

(b)the undertaker shall serve a copy of the application, and of any consent given on that application, on every person who—

(i)is registered with the undertaker in respect of any premises which are within three miles of the place where the discharge to which the application relates is proposed to be made and are not upstream from that place; and

(ii)has not agreed in writing that he need not be served with such a copy;

but, subject to paragraph (4) and without prejudice to the effect (if any) of any other contravention of the requirements of this Article in relation to such an application, a failure to provide information in pursuance of the obligation to supplement such an application shall not invalidate the application.

(3) Subject to paragraph (4), an application for a consent for the purposes of this Article shall be determined—

(a)in the case of an application with respect to a particular discharge, before the end of the period of 7 days beginning with the day after the application is made; and

(b)in any other case, before the end of the period of 3 months beginning with that day;

and, subject to that paragraph, where an application for any consent is required to be determined within the period specified in sub-paragraph (a) and is not so determined, the consent applied for shall be deemed to have been given unconditionally.

(4) Where—

(a)an undertaker which has made an application for a consent for the purposes of this Article has failed to comply with its obligation under paragraph (2)(a) to supplement that application with information required by a relevant department or the navigation authority; and

(b)that requirement was made by the relevant department or the navigation authority at such a time before the end of the period within which that department or authority is required to determine the application as gave the undertaker a reasonable opportunity to provide the required information within that period,

that department or authority may delay its determination of the application until a reasonable time after the required information is provided.

(5) A consent for the purposes of this Article may relate to a particular discharge or to discharges of a particular description and may be made subject to such reasonable conditions as may be specified by the body giving it; but a consent for those purposes shall not be unreasonably withheld.

(6) Any dispute as to whether a consent for the purposes of this Article should be given or withheld, or as to whether the conditions to which any such consent is made subject are reasonable, shall be referred to the arbitration of a single arbitrator appointed by agreement between the parties to the dispute or, in default of agreement, by the President of the Institution of Civil Engineers.

(7) Where any discharge under Article 226 is made in an emergency without the consent which, if there were no emergency, would be required by virtue of this Article, the undertaker which made the discharge shall, as soon as practicable after making the discharge, serve a notice which—

(a)states that the discharge has been made; and

(b)gives such particulars of the discharge and of the emergency as the persons served with the notice might reasonably require,

on every person on whom that undertaker would have been required to serve the application for that consent or any copy of that application.

(8) If any water undertaker contravenes, without reasonable excuse, any of the requirements of this Article or any condition of a consent given for the purposes of this Article, it shall be guilty of an offence and liable, on summary conviction, to a fine not exceeding level 3 on the standard scale.

(9) This Article does not apply in relation to a discharge which—

(a)is being made immediately before the transfer date; and

(b)is (disregarding this Article) authorised by Article 226.

(10) For the purposes of this Article the relevant departments are DARD, DOE and DCAL.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules as a PDF

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources