16.—(1) A utility must calculate the estimated value of a contract by reference to the total amount payable under it (regardless of the form of such payment), not including VAT.
(2) The total amount payable includes the amount payable as a result of the exercise of any form of option and any renewal of the contract as explicitly set out in the procurement documents.
(3) Where a utility provides for prizes or payments to candidates or tenderers it must take them into account when calculating the estimated value.
(4) Where a utility is comprised of separate operational units the utility—
(a)may calculate the estimated value by reference to each such unit or certain category thereof where that unit or certain category thereof is independently responsible for its procurement; and
(b)must calculate the estimated value by reference to the total for all the operational units which are not so responsible.
(5) A utility must not choose a method to be used to calculate the estimated value of a contract with the intention of excluding the contract from the application of these Regulations.
(6) A utility must not sub-divide a contract with the effect of excluding the contract from the application of these Regulations unless such sub-division is justified by objective reasons.
(7) The estimated value must be the value estimated at the moment at which the procurement is commenced.
(8) In the case of a framework agreement or dynamic purchasing system the estimated value shall be the total estimated value of all of the contracts envisaged pursuant to and for the total term of the agreement or system.
(9) In the case of an innovation partnership the estimated value shall be the total estimated value of the research and development activities to take place during all stages of the partnership together with the estimated value of works, supplies or services to be developed and delivered by the partner.
(10) In the case of a works contract the estimated value shall include the total estimated value of any supplies and services that are necessary for executing the works and are to be provided by the utility to the contractor.
(11) In the case of a works or service contract to be awarded in the form of separate lots, the estimated value shall be the total estimated value of all such lots.
(12) In the case of a contract for supplies which may be awarded in the form of separate lots the estimated value shall be the total estimated value of all such lots and these Regulations apply to each lot accordingly where the aggregate value of the lots is equal to or greater than the relevant threshold referred to in regulation 15 (thresholds).
(13) In the case of supply or service contracts which are regular in nature or which are intended to be renewed in a given period, the estimated value shall be calculated by reference to—
(a)the total actual value of contracts of the same type awarded during the period of 12 months or the financial year preceding the proposed award of a further contract but with adjustment of such value, where possible, to take account of the changes in quantity or value which the utility considers likely to occur during the period of 12 months following the award of the contract; or
(b)the total estimated value of the successive contracts awarded during the 12 months following the first delivery, or during the financial year.
(14) In the case of a supply contract relating to the leasing, rental, hire or hire purchase of products the estimated value shall be—
(a)in the case of a fixed term contract for a period of less than or equal to 12 months, the total estimated value of the contract;
(b)in the case of a fixed term contract for a period of more than 12 months, the total value including the estimated residual value; and
(c)in the case of a contract without a fixed term or the term of which cannot be defined, the monthly value multiplied by 48.
(15) In the case of a service contract for a service of a kind mentioned herein, the estimated value shall be calculated by reference to—
(a)for insurance services, the premium payable and any other form of remuneration;
(b)for banking and other financial services, the fees, commissions payable, interest and any other form of remuneration; and
(c)for design contracts, the fees, commissions payable and any other form of remuneration.
(16) In the case of a service contract which does not indicate a total price, the estimated value must be calculated by reference to—
(a)in the case of a contract for a fixed term of less than or equal to 48 months, the total value of the contract for its full term; and
(b)in the case of a contract for a term of more than 48 months or a contract without a fixed term, the monthly value multiplied by 48.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: