Citation, commencement, extent and application

1.—(1) These Regulations may be cited as the Late Payment of Commercial Debts (Scotland) Regulations 2013 and come into force on 29th March 2013.

(2) These Regulations extend to Scotland only.

(3) These Regulations do not affect contracts made before 29th March 2013.

Amendments of the Late Payment of Commercial Debts (Interest) Act 1998

2.—(1) Section 4 of the Late Payment of Commercial Debts (Interest) Act 1998(1) (period for which statutory interest runs) is amended as follows.

(2) After subsection (3) insert—

(3A) If, in a case where the purchaser is a public authority, the relevant day under subsection (3) would (but for this subsection) be later than the day which would be the relevant day if subsection (5) applied, it is to be treated for the purposes of subsection (3) as being the day which would be the relevant day if subsection (5) applied.

(3B) If, in a case where the purchaser is not a public authority, the relevant day under subsection (3) would (but for this subsection) be more than 30 days after the day which would be the relevant day if subsection (5) applied, it is to be treated for the purposes of subsection (3) as being the day which is 30 days after the day which would be the relevant day if subsection (5) applied.

(3C) Subsection (3B) does not apply if—

(a)the supplier and the purchaser expressly agree in the contract a date for payment of the debt that is later than the day which would otherwise be the relevant day by virtue of that subsection, and

(b)that later date is not grossly unfair to the supplier (see subsection (7A))..

(3) In subsection (5)—

(a)omit the “or” following paragraph (a); and

(b)at the end of paragraph (b), insert;

; or

(c)where subsection (5A) applies, the day determined under subsection (5B).

(4) After subsection (5) insert—

(5A) This subsection applies where—

(a)there is a procedure of acceptance or verification (whether provided for by an enactment or by the contract), under which the conforming of goods or services with the contract is to be ascertained; and

(b)the purchaser has notice of the amount of the debt on or before the day on which the procedure is completed.

(5B) For the purposes of subsection (5)(c), the day in question is the day which is 30 days after the day on which the procedure is completed.

(5C) Where, in a case where subsection (5A) applies, the procedure in question is completed after the end of the period of 30 days beginning with the day on which the obligation of the supplier to which the debt relates is performed, the procedure is to be treated for the purposes of subsection (5B) as being completed immediately after the end of that period.

(5D) Subsection (5C) does not apply if—

(a)the supplier and the purchaser expressly agree in the contract a period for completing the procedure in question that is longer than the period mentioned in that subsection; and

(b)that longer period is not grossly unfair to the supplier (see subsection (7A))..

(5) After subsection (7) insert—

(7A) In determining for the purposes of subsection (3C) or (5D) whether something is grossly unfair, all circumstances of the case shall be considered; and for that purpose, the circumstances of the case include in particular—

(a)anything that is a gross deviation from good commercial practice and contrary to good faith and fair dealing;

(b)the nature of the goods or services in question; and

(c)whether the purchaser has any objective reason to deviate from the result which is provided for by subsection (3B) or (5C)..

(6) For subsection (8) substitute—

(8) In this section—

“advance payment” has the same meaning as in section 11;

“enactment” has the same meaning as in section 126(1) of the Scotland Act 1998(2);

“public authority” means a contracting authority (within the meaning of regulation 3 of the Public Contracts (Scotland) Regulations 2012(3))..

3.—(1) Section 5A of the Late Payment of Commercial Debts (Interest) Act 1998 (compensation arising out of late payment) is amended as follows.

(2) After subsection (2) insert—

(2A) If the reasonable costs of the supplier in recovering the debt are not met by the fixed sum, the supplier shall also be entitled to a sum equivalent to the difference between the fixed sum and those costs..

(3) In subsection (3), for “an additional fixed sum” substitute “a sum”.

(4) After subsection (3) insert—

(4) Section 17(1)(b) of the Unfair Contract Terms Act 1977(4) (no reliance to be placed on certain contract terms) shall apply in cases where a contract term is not contained in written standard terms of the purchaser as well as in cases where the term is contained in such standard terms.

(5) In this section “contract term” means a term of the contract relating to a sum due to the supplier under this section..

FERGUS EWING

Authorised to sign by the Scottish Ministers

St Andrew’s House,

Edinburgh

27th February 2013

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Policy Note

Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources