The Network Rail (Waverley Steps) Order 2010

Notice of specified works

4.—(1) Network Rail shall give to the protected landowner not less than 14 days’ notice of its intention to commence construction of any specified work, or, in the case of repair carried out in an emergency, such notice as may be reasonably practicable, and notice of its completion not later than 7 days after the date on which it is brought into use.

(2) A protected landowner shall be entitled by its officer to watch and inspect the construction of any specified work.