The Network Rail (Waverley Steps) Order 2010

Articles 2(1) and 3(1)

SCHEDULE 1SCHEDULED WORKS

In the City of Edinburgh—

  • Work No. 1—Fixed stairs, the supporting structure for one or more escalators and platforms between Waverley Station and Princes Street, replacing the existing Waverley Steps.

  • Work No. 2—A pedestrian walkway across the roof of Princes Mall between Princes Street and the termination of Work No. 3.

  • Work No. 3—One or more lift shafts within Waverley Station commencing at a point adjoining platform 20 at platform level and terminating above the roof of Princes Mall, with an exit on to that roof.