10.—(1) The maximum period within which a qualifying repair is to be completed is the number of working days specified in column 2 of the Schedule opposite the defect specified in column 1 of the Schedule.
(2) The maximum period shall start on the first working day after–
(a)the date of receipt of notification of the qualifying repair by the landlord; or
(b)where the landlord inspects the house under regulation 8(a), the date of inspection.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: