Article 4
Work No. 1. A reclamation from the foreshore and bed of the sea, together with the raising of the adjoining land above high water mark, protected on its seaward face by rock armour, between reference points NF 071492 803228, NF 071517 803243, NF 071512 803283, NF 071512 803285 and NF 071455 803291.
Work No. 2. A slipway consisting of a reinforced concrete slab over rock fill, protected on its seaward face by rock armour, and a timber alignment structure, commencing at a point on Work No. 1 at reference point NF 071509 803238, extending south east for a distance of 100 metres or thereby and terminating at reference point NF 071561 803152.