- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made). Scottish Statutory Instruments are not carried in their revised form on this site.
(This note is not part of the Order)
This Order empowers the Fraserburgh Harbour Commissioners:–
(1) to deepen part of Faithlie Basin in Fraserburgh Harbour;
(2) to construct a new pier of open-work construction incorporating a shiplift in Faithlie Basin;
(3) to reclaim and fill in the existing slipway in Faithlie Basin, level adjacent land, construct ship repair bays, a ship traverser bay and boundary walls and construct a retaining wall in the South Breakwater.
The Order authorises the Commissioners to close temporarily the area of the proposed works for the purpose of carrying out the works.
The Order increases the Commissioners' borrowing limit from £5,000,000 to £6,000,000.
In relation to the election of Commissioners, the Order repeals a restriction on the number of categories of Commissioner in which a person may vote.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.