PART IIWORKS

Power to carry out works

3.—(1) Subject to the provisions of this Order, the Council may, in the situations and lines and within the limits of deviation and according to the levels shown on the deposited plan and section, carry out and maintain the following works in Aberdeenshire, and on the foreshore and bed of the sea adjacent thereto together with all necessary and proper works and conveniences connected therewith or incidental thereto:–

Work No. 1A land reclamation and a breakwater extension constructed of reinforced concrete and a rock armour revetment commencing at Point A marked on the deposited plan 25 metres north-east of the fixed point marked on the deposited plan at the north-west corner of Slipway Yard, thence extending west 110 metres to Point B marked on the deposited plan and there terminating, such works to include the demolition and removal of the existing breakwater parapet.
Work No. 2A reclamation and reconstruction in the Princes Royal Basin, consisting of a pier and a dry dock, constructed of reinforced concrete within the area shown hatched black on the deposited plan commencing at Point C marked on the deposited plan 17 metres south of the fixed point marked on the deposited plan, thence extending to Points D, E, F, G and H respectively marked on the deposited plan and terminating at Point J marked on the deposited plan 60 metres west of the fixed point marked on the deposited plan.
Work No. 3The deepening by means of excavation of the Princess Royal Basin to a depth of 5.2 metres below the level of low water within the area shown cross-hatched black on the deposited plan commencing at Point H marked on the deposited plan 48 metres west of the fixed point marked on the deposited plan and terminating at Point K marked on the deposited plan 233 metres south west of the fixed point marked on the deposited plan.
Work No. 4AThe construction of an underpinning in the Princess Royal Basin of width 1 metre commencing at Point J marked on the deposited plan 60 metres west of the fixed point marked on the deposited plan and terminating at Point K marked on the deposited plan 233 metres south-west of the fixed point marked on the deposited plan.
Work No. 4BThe construction of an underpinning in the Princess Royal Basin of width 1 metre commencing at Point L marked on the deposited plan 36 metres south-west of the fixed point marked on the deposited plan and terminating at Point M marked on the deposited plan 93 metres west-south-west of the fixed point marked on the deposited plan.
Work No. 4CThe construction of an underpinning in the Princess Royal Basin of width 1 metre commencing at Point N marked on the deposited plan 48 metres south-south-west of the fixed point marked on the deposited plan and terminating at Point P marked on the deposited plan 220 metres south-west of the fixed point marked onthe deposited plan.
Work No. 5The construction of a spending slope in the Princess Royal Basin, consisting of rock armour stones within the area shown hatched black on the deposited plan commencing at Point R marked on the deposited plan 42 metres south-west of the fixed point marked on the deposited plan and terminating at Point S marked on the deposited plan 33 metres south-south-west of the fixed point marked on the deposited plan, such works to include the demolition of the existing revetment.

(2) The Council may, within the limits of deviation, maintain, renew, reconstruct and alter temporarily or permanently the works.

(3) Subject to the provisions of this Order no material dredged at Work No. 3 shall be deposited below the level of high water except in such places and in accordance with such conditions and restrictions as may be approved or prescribed by Scottish Ministers.