SCHEDULE 1ACTIVITIES AND INSTALLATIONS AND MOBILE PLANT
PART 1ACTIVITIES
CHAPTER 3: MINERAL INDUSTRIES
SECTION 3.1: Production of cement, lime and magnesium oxide
- a
Producing cement clinker in rotary kilns with a production capacity exceeding 500 tonnes per day or in other kilns with a production capacity exceeding 50 tonnes per day,
- b
Producing lime or magnesium oxide in kilns with a production capacity exceeding 50 tonnes per day.
- a
Any of the following activities:—
- i
storing, loading or unloading cement or cement clinker in bulk prior to further transportation in bulk,
- ii
blending cement in bulk or using cement in bulk other than at a construction site, including the bagging of cement and cement mixture, the batching of ready-mixed concrete and the manufacture of concrete blocks and other cement products,
- iii
grinding cement clinker.
- i
- b
Slaking lime for the purpose of making calcium hydroxide or calcium magnesium hydroxide.
- c
Heating calcium carbonate or calcium magnesium carbonate for the purpose of making lime.