5.—(1) Subject to article 9, electricity shall be considered to have been generated from eligible renewable sources to the extent that it has been generated from renewable sources and provided that it has not been generated by an excluded generating station as specified in this article and articles 6 and 7.

(2) The following shall be excluded generating stations–

(a)large hydro generating stations except those first commissioned after 1st April 2002;

(b)subject to paragraphs (3) and (4), generating stations (other than micro hydro generating stations) which were first commissioned before 1st January 1990 and where the main components have not been renewed since 31st December 1989 as described in paragraph (5);

(c)generating stations located outside the United Kingdom, except generating stations which are not located on land and which are directly and exclusively connected to a transmission or distribution network located in Northern Ireland; and

(d)generating stations generating electricity under the arrangements or additional arrangements referred to in article 35(1) of the Northern Ireland Electricity Order.

(3) A generating station shall not be an excluded generating station by virtue of paragraph (2)(b) in any month during which it is fuelled partly by fossil fuel and partly by biomass (and by no other fuel).

(4) A generating station shall be an excluded generating station by virtue of paragraph (2)(b) in any month during which it is fuelled by biomass, if–

(a)prior to 1st April 2003 at least 75 per cent of the energy content of the fuel by which it was fuelled was derived from fossil fuel; and

(b)during no month (being a month after March 2004) after the first month during which it was fuelled wholly by biomass has the energy content of the fuel by which it was fuelled been derived as to more than 75 per cent from fossil fuel.

(5) For the purposes of paragraph (2)(b), the main components of a generating station shall only be regarded as having been renewed since 31st December 1989 where–

(a)in the case of a hydro generating station, the following parts have been installed in the generating station after 31st December 1989 and were not used for the purpose of electricity generation prior to that date–

(i)either all the turbine runners or all the turbine blades or the propeller; and

(ii)either all the inlet guide vanes or all the inlet guide nozzles; or

(b)in the case of any other generating station all the boilers and turbines (driven by any means including wind, water, steam or gas) have been installed in the generating station after 31st December 1989 and were not used for the purpose of electricity generation prior to that date.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Draft Executive Notes

Draft Executive Note sets out a brief statement of the purpose of a Draft Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources