4.—(1) For the purposes of these regulations, the area shown on the official map and named as “North Eastern” is identified as a river basin district and the areas shown on the official map and named as “Neagh Bann”, “North Western” and “Shannon” are identified as international river basin districts.
(2) The Department must publish the official map on its website.
(3) The Department must make the official map available to the public at its principal offices.
(4) In this regulation, “the official map” means the map of river basin districts produced by the Department and published on its website.
5.—(1) The Department must maintain and periodically review and (if necessary) update, in accordance with Annex II to the Directive (characterisation of waters)—
(a)an analysis of the characteristics of each river basin district and the part of each international river basin district falling within Northern Ireland; and
(b)a review of the impact of human activity on the status of surface water and groundwater in the river basin district and the part of each international river basin district falling within Northern Ireland.
(2) A review and any update must be done—
(a)by 22nd December 2019; and
(b)subsequently, by 22nd December of the sixth year following that date and of each sixth year following that.
(3) In relation to a review of the characteristics of each river basin district and part of each international river basin district falling within Northern Ireland in accordance with paragraph 1(a), the Department must include in the relevant river basin management plan an explanation of the approach taken to the use of System A or B in paragraphs 1.1 and 1.2 to 1.2.4 (characterisation of surface water body types) of Annex II to the Directive.
6. The Department must classify the status of bodies of water in accordance with Annex V to the Directive.
7.—(1) The Department must maintain and periodically review and (if necessary) update, in accordance with Annex III to the Directive (economic analysis), an economic analysis of water use in the river basin district and the part of each international river basin district falling within Northern Ireland.
(2) A review and any update must be done—
(a)by 22nd December 2019; and
(b)subsequently, by 22nd December of the sixth year following that date and of each sixth year following that.
(3) The Department for Infrastructure must, in accordance with a timetable established by the Department—
(a)provide the Department with so much of the information specified in paragraph (a) of Annex III to the Directive as relates to its functions;
(b)review and, if necessary, update that information; and
(c)provide any such updated information to the Department.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Rule and provides information about its policy objective and policy implications. They aim to make the Statutory Rule accessible to readers who are not legally qualified and accompany any Northern Ireland Statutory Rule or Draft Northern Ireland Statutory Rule laid before the UK Parliament during the suspension of the Northern Ireland Assembly.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: