xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 6COMPENSATION IN RELATION TO OFF-SITE CONDITIONS

6.—(1) The amount to be paid by way of compensation under this Schedule shall be assessed in accordance with the following sub-paragraphs.

(2) The rules set out in Article 6 of the Land Compensation (Northern Ireland) Order 1982(1) (rules for assessing compensation) shall, so far as applicable and subject to any necessary modifications, have effect for the purposes of this paragraph as they have effect for the purpose of assessing compensation for the compulsory acquisition of an interest in land.

(3) No account shall be taken of any enhancement of the value of any interest in land, by reason of any building erected, work done or improvement or alteration made on any land in which the grantor is, or was at the time of erection, doing or making, directly or indirectly concerned, if the Lands Tribunal is satisfied that the erection of the building, the doing of the work, the making of the improvement or the alteration was not reasonably necessary and was undertaken with a view to obtaining compensation or increased compensation.

(4) In calculating the amount of any loss under paragraph 3(e) expenditure incurred in the preparation of plans or on other similar preparatory matters, shall be taken into account.

(5) Where the interest in respect of which compensation is to be assessed is subject to a mortgage—

(a)the compensation shall be assessed as if the interest were not subject to the mortgage; and

(b)no compensation shall be payable in respect of the interest of the mortgagee (as distinct from the interest which is subject to the mortgage).

(6) Compensation under this Schedule shall include an amount equal to the grantor’s reasonable valuation and legal expenses.