SCHEDULES
SCHEDULE 1ACTIVITIES, INSTALLATIONS AND MOBILE PLANT
PART 1ACTIVITIES
CHAPTER 1ENERGY INDUSTRIES
SECTION 1.1COMBUSTION ACTIVITIES
Part A
a
Burning any fuel in an appliance with a rated thermal input of 50 megawatts or more.
Interpretation of Part A
1
Where two or more appliances with an aggregate rated thermal input of 50 megawatts or more are operated on the same site by the same operator those appliances shall be treated as a single appliance with a rated thermal input of 50 megawatts or more.
Part B
Nil.
Part C
a
Unless falling within Part A of this section, burning any fuel, in a boiler or furnace or a gas turbine or compression ignition engine with, in the case of any of these appliances, a net rated thermal input of 20 megawatts or more but less than a rated thermal input of 50 megawatts.
Interpretation of Part C
1
Nothing in this Part applies to any activity falling within Part A of section 5.1.