Table 1 (Marine Construction Licence) is categorised into 9 bands which reflect the size and scale of the project, in monetary terms. The applicant will be required to pay the licence fee (Column 2) on submission of an application.

2.

Tables 2 (Maintenance Dredging Licence), 3 (Capital Dredging Licence), 4 (Maintenance Dredge Disposal Licence) and 5 (Capital Dredge Disposal Licence) are all categorised into bands which reflect the metric tonnages of material to be dredged or disposed of. In each case, the applicant will be required to pay the Licence Fee (Column 2) on submission of an application.

3.

Tables 6 (Deposit of Tracer Dyes, Biocides and Other Such Materials Licence) and 7 (Marine Minerals Extraction Licence) each have a single band. The fee to be paid by the applicant on submission of an application is as indicated.

4.

Table 8 (Marine Renewable Energy Licence) is categorised into 4 bands which reflect the size and scale of the project, in terms of its output in Megawatts. The applicant will be required to pay the Licence Fee (Column 2) on submission of an application.

PART 2FEES PAYABLE (AMOUNTS PAYABLE)

Table 1

Marine Construction Licence

Column 1

Banded values in monetary terms

Column 2

Licence Fee

Band A

Up to £19,999

£550

Band B

£20,000 - £49,999

£759

Band C

£50,000 - £199,999

£1,446

Band D

£200,000 - £499,999

£2,075

Band E

£500,000 - £999,999

£2,410

Band F

£1,000,000 - £2,999,999

£4,506

Band G

£3,000,000 - £4,999,999

£5,554

Band H

£5,000,000 - £19,999,999

£6,602

Band I

£20,000,000 and above

£10,795

Table 2

Maintenance Dredging Licence

Column 1

Banded values in terms of mass of material dredged.

(t = tonne)

Column 2

Licence Fee

Band 1

0 – 9,999t

£250

Band 2

10,000t – 24,999t

£300

Band 3

25,000t – 49,999t

£350

Table 3

Capital Dredging Licence

Column 1

Banded values in terms of mass of material dredged.

(t = tonne)

Column 2

Licence Fee

Band 1

0 – 9,999t

£902

Band 2

10,000t – 24,999t

£1,253

Band 3

25,000t – 49,999t

£1,704

Band 4

50,000t – 99,999t

£2,405

Band 5

100,000t – 499,999t

£3,358

Band 6

500,000t – 999,999t

£4,761

Band 7

1,000,000t and above

£8,019

Table 4

Maintenance Dredge Disposal Licence

Column 1

Banded values in terms of mass of material disposed.

(t = tonne)

Column 2

Licence Fee

Band 1

0 – 9,999t

£2,017

Band 2

10,000t – 24,999t

£2,751

Band 3

25,000t – 49,999t

£3,856

Band 4

50,000t – 99,999t

£5,428

Band 5

100,000t – 499,999t

£7,650

Band 6

500,000t – 999,999t

£10,795

Band 7

1,000,000t and above

£18,131

Table 5

Capital Dredge Disposal Licence

Column 1

Banded values in terms of mass of material disposed.

(t = tonne)

Column 2

Licence Fee

Band 1

0 – 9,999t

£2,709

Band 2

10,000t – 24,999t

£3,715

Band 3

25,000t – 49,999t

£5,208

Band 4

50,000t – 99,999t

£7,367

Band 5

100,000t – 499,999t

£10,365

Band 6

500,000t – 999,999t

£14,672

Band 7

1,000,000t and above

£24,723

Table 6

Deposit of Tracer Dyes, Biocides and Other Such Materials Licence

Licence Fee
£419

Table 7

Marine Minerals Extraction Licence

Licence Fee
£29,345

Table 8

Marine Renewable Energy Licence

Column 1

Banded values in terms of the project’s power output.

(MW = Megawatts)

Column 2

Licence Fee

Band R1

0 – 0.99MW

£4,009

Band R2

1.0MW – 9.99MW

£12,530

Band R3

10MW – 99.9MW

£20,550

Band R4

100MW and above

£30,574