PART 4Implementation and discharge of liability

Notification about the implementation period by the BoardI110

1

Within a period of 21 days beginning on the day on which the implementation period begins in accordance with section 93(1), the Board must notify the transferor and transferee of the date that the implementation period began.

2

Where the implementation period cannot begin because the Board has not received all of the documents or information specified in section 93(1)(b)(i) and regulation 7(1) or (3), the Board must, as soon as practicable after becoming aware that it has not received all such documents and information—

a

notify the transferor and the transferee, or (in cases where the transferee has died before the implementation period has begun) the executor or personal representative of the transferee, that the start of the implementation period is delayed because the Board has not been supplied with relevant information, and

b

specify the information required and (if applicable) the date on which it was requested.

3

Where the implementation period—

a

is extended in accordance with regulation 8, or

b

is postponed or ceases to operate in accordance with regulation 9,

the Board must, within 21 days of the date of the extension, postponement or cessation of the implementation period, notify the transferor and transferee of the reasons for that extension, postponement or cessation, including details of any information which the Board requires in order to complete implementation.

4

If any charges imposed by the Board in accordance with regulation 16 are due or will become due to be paid, the Board must notify the transferor and transferee of—

a

the amount of the charges;

b

the party who, in accordance with section 95(3), is responsible for paying the charges;

c

the date on which the charges were due or will become due to be paid;

d

the method, in accordance with regulation 16(4), by which the charges may be recovered if not paid by the date specified in sub-paragraph (c), and

e

the date, calculated in accordance with regulation 16(6)(e), on or after which the Board may recover the charges if not paid by the date specified in sub-paragraph (c).