Measuring Instruments (EEC Requirements) (Verification Fees) Regulations (Northern Ireland) 2009

Regulation 5(1) and (2)

SCHEDULE 2

In this Schedule, the abbreviation employed to refer to the kilogramme unit of measurement is kg.

NOTE – previous fees in brackets£
A. Weighing Instruments —
(1) subject to single EC verification, each instrument or (if fitted with two or more weigh tables or platforms connected to one or more indicating mechanisms), each weigh table or platform —
capacity as marked on the machine —
not exceeding 100 kg24.00(23.00)
exceeding 100 kg but not exceeding 1,000 kg51.50(50.00)
exceeding 1,000 kg but not exceeding 5,000 kg122.00(118.00)
exceeding 5,000 kg but not exceeding 30,000 kg266.50(258.00)
exceeding 30,000 kg398.50(386.00)
(2) subject to two stages of EC verification, each stage verification50 per cent of the fee which would be payable if the weighing instrument were only subject to a single stage EC verification
B. Otherwise, each verification —
per man/hour spent at the place of verificationInspector rate 39.00(38.00)
Assistant rate 28.00(27.00)