SCHEDULE 5PARTICULARS TO BE INCLUDED IN A NOTIFICATION OF COMBINED OPERATIONS

Regulation 10(1)

I11

The name and address of each duty holder preparing the notification and a confirmation that every such duty holder has agreed to the contents of the notification.

I22

A description of how the management systems for the installations involved in the combined operation will be co-ordinated so as to reduce the risks from a major accident to comply with the relevant statutory provisions.

I33

Particulars of any plant to be used in connection with the combined operation but which is not described in the current safety case for any of the installations involved in the combined operation.

I44

A summary of the joint review referred to in paragraph 14(b) of Schedule 3 or paragraph 13(b) of Schedule 4, which shall include—

a

a description of any activities during the combined operation which may involve hazards with the potential to cause a major accident on or in connection with an installation; and

b

a description of any risk control measures introduced as a result of that review.

I55

A description of the combined operation and a programme of work, which shall include the dates on which the combined operation is expected to commence and finish.