Renewables Obligation Order (Northern Ireland) 2005

This section has no associated Explanatory Memorandum

17.—(a) This paragraph applies where an extant qualifying arrangement (“the applicable qualifying arrangement”) provides for the building of a generating station (“the specified station”) at a specified location (“the location”) and the specified station has not been commissioned.

(b)If this paragraph applies then it is a condition of eligibility that the electricity to which the GBROC relates was not generated by a generating station which is situated at the location and which is owned or operated by a person who is a party to the applicable qualifying arrangement, or is a connected person or a linked person in relation to any such party.

(c)This paragraph does not apply to a GBROC relating to electricity generated by a generating station which, during the month in question, generates only electricity which is sold pursuant to another extant qualifying arrangement.