10. Where an environmental statement is required in relation to an application for planning permission, article 11 of the General Development Order shall have effect as if—
(a)for the reference in paragraph (2)(a) of that article to a period of 2 months from the date the application was received there were substituted a reference to a period of 16 weeks; and
(b)after paragraph (3)(b) of that article there were inserted—
“(ba)the environmental statement required to be submitted in respect of the application has been submitted, together with the documents required to accompany that statement; and”.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: