xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 2N.I.CROWN APPLICATION – TRANSITIONAL PROVISIONS

PART 2 N.I.LISTED BUILDINGS CONSENT AND CONSERVATION AREA CONSENT

IntroductionN.I.

6.  This Part applies to works if—N.I.

(a)they are works for which before the relevant date no listed building consent is required, and

(b)before the relevant date proposed works notice had been given to the Department.

7.  In this Part—N.I.

(a)the relevant date is the date of the coming into operation of Article 21(1);

(b)proposed works notice is notice of a proposal for works given by the person proposing to carry out the works (the developer) in pursuance of arrangements made by the Department in relation to development by or on behalf of the Crown;

(c)the developer is the Crown or a person acting on behalf of the Crown.