SCHEDULES

Prospective

SCHEDULE 6N.I.Extension by panel of public protection order without restrictions

Time limit for panel's decision, and duty to notify decisionN.I.

9—(1) The panel must comply with paragraph 8(1) as soon as practicable and in any case no later than the end of the permitted period.N.I.

(2) The “permitted period” is 7 working days beginning with the day on which the application is received by the trust (or, if that day is not a working day, beginning with the first working day after that).

(3) As soon as practicable after granting or refusing an extension under paragraph 8, the panel must give written notice of the grant or refusal, and any prescribed information, to the person concerned and any prescribed person.