Section 73 – Department’s power to arrange taking of safety measures
Where a reservoir manager fails to comply with such an enforcement notice, the department may commission a relevant engineer to supervise the taking of the measure. Subsection (3) requires the engineer commissioned to provide the Department with a certificate when the engineer is satisfied that the measure has been taken. The engineer’s certificate has the same effect as if it were an interim inspection compliance certificate or an inspection compliance certificate or a safety measure certificate as appropriate. Subsection (6) enables the Department, if it considers it appropriate, by notice require the reservoir manager to pay the Department such amount of associated costs reasonably incurred. Subject to right of appeal (section 76) the reservoir manager must pay any costs so incurred and specified in the notice (subsection (7)).