Regulation (EU) No 1303/2013 of the European Parliament and of the CouncilShow full title

Regulation (EU) No 1303/2013 of the European Parliament and of the Council of 17 December 2013 laying down common provisions on the European Regional Development Fund, the European Social Fund, the Cohesion Fund, the European Agricultural Fund for Rural Development and the European Maritime and Fisheries Fund and laying down general provisions on the European Regional Development Fund, the European Social Fund, the Cohesion Fund and the European Maritime and Fisheries Fund and repealing Council Regulation (EC) No 1083/2006

CHAPTER II U.K. Major projects

Article 100U.K.Content

As part of an operational programme or operational programmes, which have been subject to a Commission decision under Article 96(10) of this Regulation or under Article 8(12) of the ETC Regulation, the ERDF and the Cohesion Fund may support an operation comprising a series of works, activities or services intended in itself to accomplish an indivisible task of a precise economic or technical nature which has clearly identified goals and for which the total eligible cost exceeds EUR 50 000 000 and in the case of operations contributing to the thematic objective under point (7) of the first paragraph of Article 9 where the total eligible cost exceeds EUR 75 000 000 (the 'major project'). Financial instruments shall not be considered to be major projects.

Article 101U.K.Information necessary for the approval of a major project

Before a major project is approved, the managing authority shall ensure that the following information is available:

(a)

details concerning the body to be responsible for implementation of the major project, and its capacity;

(b)

a description of the investment and its location;

(c)

the total cost and total eligible cost, taking account of the requirements set out in Article 61;

(d)

feasibility studies carried out, including the options analysis, and the results;

(e)

a cost-benefit analysis, including an economic and a financial analysis, and a risk assessment;

(f)

an analysis of the environmental impact, taking into account climate change adaptation and mitigation needs, and disaster resilience;

(g)

an explanation as to how the major project is consistent with the relevant priority axes of the operational programme or operational programmes concerned, and its expected contribution to achieving the specific objectives of those priority axes and the expected contribution to socio-economic development;

(h)

the financing plan showing the total planned financial resources and the planned support from the Funds, the EIB, and all other sources of financing, together with physical and financial indicators for monitoring progress, taking account of the identified risks;

(i)

the timetable for implementing the major project and, where the implementation period is expected to be longer than the programming period, the phases for which support from the Funds is requested during the programming period.

The Commission shall adopt implementing acts establishing the methodology to be used based on recognised best practices, in carrying out the cost-benefit analysis referred to in point (e) of the first paragraph. Those implementing acts shall be adopted in accordance with the advisory procedure referred to in Article 150(2).

At the initiative of a Member State, the information in points (a) to (i) of the first paragraph may be assessed by independent experts supported by technical assistance of the Commission or, in agreement with the Commission, by other independent experts ("quality review"). In other cases, the Member State shall submit to the Commission the information set out in points (a) to (i) of the first paragraph as soon as it is available.

The Commission shall be empowered to adopt delegated acts, in accordance with Article 149, laying down the methodology to be used in carrying out the quality review of a major project.

The Commission shall adopt implementing acts establishing the format for submission of the information set out in points (a) to (i) of the first paragraph. Those implementing acts shall be adopted in accordance with the advisory procedure referred to in Article 150(2).

Article 102U.K.Decision on a major project

1.Where a major project has been appraised positively by a quality review by independent experts, on the basis of their assessment of the information referred to in the first paragraph of Article 101, the managing authority may proceed with the selection of the major project in accordance with Article 125(3). The managing authority shall notify the Commission of the selected major project. That notification shall consist of the following elements:

(a)the document referred to in point (c) of Article 125(3) setting out:

(i)

the body to be responsible for implementation of the major project;

(ii)

a description of the investment, its location, timetable and expected contribution of the major project to the specific objectives of the relevant priority axis or axes;

(iii)

the total cost and total eligible cost, taking account of the requirements set out in Article 61;

(iv)

the financing plan, and the physical and financial indicators for monitoring progress, taking account of the identified risks;

(b)the quality review of the independent experts, providing clear statements on the investment's feasibility and the economic viability of the major project.

The financial contribution to the major project selected by the Member State shall be deemed to be approved by the Commission in the absence of a decision, by means of an implementing act, refusing the financial contribution within three months of the date of the notification referred to in the first subparagraph. The Commission shall refuse the financial contribution only on the grounds that it has established a significant weakness in the independent quality review.

The Commission shall adopt implementing acts establishing the format for the notification referred to in the first subparagraph. Those implementing acts shall be adopted in accordance with the examination procedure referred to in Article 150(3).

2.In cases other than those referred to in paragraph 1 of this Article, the Commission shall appraise the major project on the basis of the information referred to in Article 101 in order to determine whether the requested financial contribution for the major project selected by the managing authority in accordance with Article 125(3) is justified. The Commission shall adopt a decision on the approval of the financial contribution to the selected major project, by means of an implementing act, no later than three months after the date of submission of the information referred to in Article 101.

3.The approval by the Commission under the second subparagraph of paragraph 1 and paragraph 2 shall be conditional on the first works contract being concluded, or, in the case of operations implemented under PPP structures, on the signing of the PPP agreement between the public body and the private sector body, within three years of the date of the approval. At the duly motivated request of the Member State, in particular in the case of delays resulting from administrative and legal proceedings related to the implementation of major projects, and made within the three year period, the Commission may adopt a decision, by means of an implementing act, on the extension of the period by not more than two years.

4.Where the Commission does not approve the financial contribution to the selected major project, it shall give in its decision the reasons for its refusal.

5.Major projects notified to the Commission under paragraph 1 or submitted for approval under paragraph 2 shall be contained in the list of major projects in an operational programme.

[F16. Expenditure relating to a major project may be included in a payment application after the submission for approval referred to in paragraph 2. Where the Commission does not approve the major project selected by the managing authority, the declaration of expenditure following the withdrawal of the application by the Member State or the adoption of the Commission decision shall be rectified accordingly.]

[F27. Where the major project is appraised by independent experts pursuant to paragraph 1 of this Article, expenditure relating to that major project may be included in a payment application after the managing authority has informed the Commission of the submission to the independent experts of the information required under Article 101.

An independent quality review shall be delivered within six months of the submission of that information to the independent experts.

The corresponding expenditure shall be withdrawn and the declaration of expenditure shall be rectified accordingly in the following cases:

(a) where the independent quality review has not been notified to the Commission within three months of the expiry of the deadline referred to in the second subparagraph;

(b) where the submission of the information is withdrawn by the Member State; or

(c) where the relevant appraisal is negative.]

Article 103U.K.Decision on a major project subject to phased implementation

1.By way of derogation from the third paragraph of Article 101 and Article 102(1) and (2), the procedures set out in paragraphs 2, 3 and 4 of this Article shall apply to an operation which satisfies the following conditions:

(a)the operation consists of the second or subsequent phase of a major project under the previous programming period for which the preceding phase or phases are approved by the Commission not later than 31 December 2015 pursuant to Regulation (EC) No 1083/2006; or in the case of Member States which acceded to the Union after 1 January 2013, no later than 31 December 2016;

(b)the sum of the total eligible costs of all phases of the major project exceeds the respective levels set out in Article 100;

(c)the major project application and assessment by the Commission under the previous programming period covered all the planned phases;

(d)there are no substantial changes in the information referred to in the first paragraph of Article 101 of this Regulation for the major project compared to the information provided for the major project application submitted under Regulation (EC) No 1083/2006, in particular as regards the total eligible cost;

(e)the phase of the major project to be implemented under the previous programming period is or will be ready to be used for its intended purpose as specified in the Commission decision by the deadline of the submission of the closure documents for the relevant operational programme or programmes.

2.The managing authority may proceed with the selection of the major project in accordance with Article 125(3) and submit the notification containing all the elements set out in point (a) of the first subparagraph of Article 102(1) together with its confirmation that the condition under point (d) of paragraph 1 of this Article is fulfilled. No quality review of the information by independent experts shall be required.

3.The financial contribution to the major project selected by the managing authority shall be deemed to be approved by the Commission in the absence of a decision, by means of an implementing act, refusing the financial contribution to the major project within three months of the date of the notification referred to in paragraph 2. The Commission shall refuse the financial contribution only on the grounds that there have been substantial changes in the information referred to in point (d) of paragraph 1 or that the major project is not consistent with the relevant priority axis of the operational programme or programmes concerned.

4.Article 102(3) to (6) shall apply to decisions on a major project subject to phased implementation.