- Latest available (Revised)
- Original (As adopted by EU)
Decision (EU) 2016/245 of the European Central Bank of 9 February 2016 laying down the rules on procurement (ECB/2016/2) (recast)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
This version of this Decision was derived from EUR-Lex on IP completion day (31 December 2020 11:00 p.m.). It has not been amended by the UK since then. Find out more about legislation originating from the EU as published on legislation.gov.uk.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.When fixing the time limits for the receipt of applications and tenders, the ECB shall take account in particular of the complexity of the contract and the time required for drawing up tenders, without prejudice to the minimum time limits set by this Article.
2.In the case of open procedures, the minimum time limit for the receipt of tenders shall be 35 days from the date on which the contract notice was sent to the Official Journal.
3.In the case of restricted procedures, negotiated procedures, competitive dialogues, innovation partnerships and design contests:
(a)the minimum time limit for receipt of applications shall be 30 days from the date on which the contract notice was sent to the Official Journal; and
(b)the minimum time limit for the receipt of tenders shall be 30 days from the date on which the invitation to tender was sent to the tenderers.
4.When a prior information notice has been published in the Official Journal containing the information set out in Article 48(2) of Directive 2014/24/EU, which was sent between 35 days and 12 months before the contract notice, the minimum time limit for the receipt of tenders may, as a general rule, be shortened to 15 days for open and 10 days for restricted procedures.
5.The time limits for the receipt of applications and tenders may be shortened by 5 days when fully electronic procurement is used, unless paragraph 4 applies.
6.In the case of open procedures, restricted procedures and negotiated procedures, the ECB may apply an accelerated procedure, where duly substantiated urgency renders impracticable the time limits laid down in this Article. In this case the following minimum time limits shall apply:
(a)for open procedures a time limit for the receipt of tenders which is not less than 15 days from the date on which the contract notice was sent; and
(b)for restricted procedures and negotiated procedures a time limit for the receipt of applications which shall be not less than 15 days from the date on which the contract notice was sent, and a time limit for the receipt of tenders which shall be not less than 10 days from the date on which the invitation to tender was sent to the tenderers.
7.Prior to the expiry date, the ECB may extend the time limits set out in the contract notice or procurement documents if it significantly modifies the procurement documents or in other duly justified cases, subject to the principle of equal treatment.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: