Decision (EU) 2016/245 of the European Central Bank of 9 February 2016 laying down the rules on procurement (ECB/2016/2) (recast)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
This version of this Decision was derived from EUR-Lex on IP completion day (31 December 2020 11:00 p.m.). It has not been amended by the UK since then. Find out more about legislation originating from the EU as published on legislation.gov.uk.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.The ECB may carry out a competitive dialogue in the cases outlined in Article 12(1).
2.On publication of a contract notice interested suppliers may apply for participation in the dialogue. They shall submit their application within the time limit specified in the contract notice and provide the documentation requested by the ECB.
3.The ECB shall verify the eligibility of candidates and evaluate the applications against the selection criteria set out in the contract notice. The ECB shall invite at least three eligible candidates to participate in the dialogue and provide them with a request for a proposal setting out the ECB's needs. The aim of the dialogue is to identify and define the solution that is best suited to meet the ECB's needs. The ECB may discuss all aspects of the contract with the candidates. The number of candidates invited shall be sufficient to ensure genuine competition. If the number is below the minimum number, the ECB may continue the procedure with all candidates meeting the selection criteria.
4.The dialogue shall be carried out within the timeframe set out in the contract notice. During the dialogue, the ECB shall ensure equal treatment of all participants. The ECB may not provide any information which may give some participants an advantage over others or reveal to other participants solutions proposed or other confidential information communicated by a candidate participating in the dialogue without their specific written agreement thereto.
5.If the contract notice so provides, the ECB may carry out the dialogue in successive stages to reduce the number of solutions to be discussed during the dialogue stage. The ECB shall continue the dialogue until it can identify the solution or solutions which are capable of meeting its needs. The ECB shall select the solutions to be considered by applying the award criteria set out in the contract notice or the request for a proposal.
6.Having declared that the dialogue is concluded, the ECB shall ask the candidates participating in the dialogue to submit their final tenders on the basis of the solutions presented and specified during the dialogue. The ECB may request the tenderers to clarify, specify or optimise certain aspects of their tenders or to confirm commitments contained in the tender provided that this does not have the effect of modifying substantial aspects of the tender and does not risk distorting competition or causing discrimination.
7.The ECB shall evaluate the tenders received against the award criteria laid down in the contract notice or the request for a proposal. Once the evaluation is completed, the ECB shall award the contract to the tenderer whose tender best meets the award criteria, which must include quality aspects.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: