PART 2Compensation in relation to conditions affecting certain interests in land

Interpretation

20.  In this Part—

“grantor” means a person who grants the operator rights pursuant to regulation 15(2);

“relevant interest” means an interest in land out of which rights have been granted pursuant to regulation 15(2);

“rights” means the rights granted by the grantor.

Entitlement to compensation

21.  A grantor is entitled to be paid compensation under this Part by the operator.

Loss and damage for which compensation is payable

22.  Subject to paragraph 25(3) and 25(5)(b), compensation is payable for loss and damage of the following descriptions—

(a)depreciation in the value of any relevant interest to which the grantor is entitled which results from the grant of the rights;

(b)depreciation in the value of any other interest in land to which the grantor is entitled which results from the exercise of the rights;

(c)loss or damage, in relation to any relevant interest to which the grantor is entitled, which—

(i)is attributable to the grant of the rights or the exercise of them,

(ii)does not consist of depreciation in the value of that interest, and

(iii)is loss or damage for which he would have been entitled to compensation by way of compensation for disturbance, if that interest had been acquired compulsorily—

(aa)under the Acquisition of Land Act 1981(1), and

(bb)in pursuance of a notice to treat served on the date on which the rights were granted;

(d)damage to, or injurious affection of, any interest in land to which the grantor is entitled which—

(i)is not a relevant interest, and

(ii)results from the grant of the rights or the exercise of them;

(e)loss in respect of work carried out by or on behalf of the grantor which is rendered abortive by the grant of the rights or the exercise of them.

Date when entitlement to compensation arises

23.—(1) An entitlement to compensation under this Part arises on the date of the grant of the rights.

(2) But if an appeal against the conditions of the environmental permit which rendered the grant of rights necessary is refused, the entitlement to compensation arises on the date the appeal is finally determined.

Application for compensation

24.—(1) An application for compensation under this Part must be made by the grantor—

(a)within 12 months of the date on which the entitlement to compensation arises; or

(b)within 6 months of the date on which the rights are first exercised.

(2) An application must be—

(a)made in writing;

(b)made to the operator to whom the rights were granted; and

(c)delivered at or sent by pre-paid post to the last known address for correspondence of that operator.

(3) The application must contain, or be accompanied by—

(a)a copy of the grant of rights in respect of which the grantor’s entitlement arises and any plans attached to that grant;

(b)a description of the exact nature of any interest in land in respect of which compensation is applied for;

(c)a statement of the amount of compensation applied for—

(i)distinguishing the amounts applied for under each of paragraphs 22(a) to 22(e), and

(ii)showing how the amount applied for under each paragraph has been calculated; and

(d)if the date on which the entitlement to compensation arises is ascertained in accordance with paragraph 23(2), a copy of the notice of the final determination of the appeal.

Assessment of the amount to be paid by way of compensation

25.—(1) The amount to be paid by way of compensation under this Part must be assessed in accordance with this paragraph.

(2) The rules set out in section 5 of the Land Compensation Act 1961(2) have effect for the purposes of this paragraph as they have effect for the purpose of assessing compensation for the compulsory acquisition of an interest in land, so far as applicable and subject to any necessary modifications.

(3) No account is to be taken of any enhancement of the value of an interest in land by reason of any building erected, work done, or improvement or alteration made on land in which the grantor is, or was at the time of erection, doing or making, directly or indirectly concerned if the erection of the building, the doing of the work, the making of the improvement or the alteration was not reasonably necessary and was undertaken with a view to obtaining compensation or increased compensation.

(4) In calculating the amount of a loss under paragraph 22(e), expenditure incurred in the preparation of plans or on other similar preparatory matters must be taken into account.

(5) Where the interest in respect of which compensation is to be assessed is subject to a mortgage—

(a)the compensation must be assessed as if the interest were not subject to the mortgage; and

(b)no compensation is payable in respect of the interest of the mortgagee (as distinct from the interest which is subject to the mortgage).

(6) Compensation must include an amount equal to the grantor’s reasonable valuation and legal expenses.

Payment of compensation

26.—(1) Compensation in respect of an interest which is subject to a mortgage must be paid—

(a)to the mortgagee; or

(b)if there is more than one mortgagee, to the first mortgagee,

and must, in either case, be applied by him as if it were proceeds of sale.

(2) Amounts of compensation determined under this Part are payable—

(a)where the operator and the grantor or mortgagee agree that a single payment is to be made on a specified date, on that date;

(b)where the operator and the grantor or mortgagee agree that payment is to be made in instalments at different dates, on the date agreed as regards each instalment;

(c)in any other case, subject to any direction of the Lands Tribunal or the court, as soon as reasonably practicable after the amount of the compensation has been finally determined.

(3) Any question of the application of paragraph 25(3) or dispute as to the amount of compensation must be referred to and determined by the Lands Tribunal.

(4) In relation to the determination of such a question, sections 2 and 4 of the Land Compensation Act 1961(3) apply as if—

(a)the reference in section 2(1) of that Act to section 1 of that Act were a reference to sub-paragraph (3) of this paragraph; and

(b)references in section 4 of that Act to the acquiring authority were references to the operator.

Interest payable on compensation

27.—(1) Compensation payable under this Part carries interest at the rate for the time being prescribed under section 32 of the Land Compensation Act 1961 from the date specified in sub-paragraph (2) to payment.

(2) The date is—

(a)in the case of compensation payable under paragraph 22(a) or 22(b), the date of depreciation;

(b)in the case of compensation payable under paragraph 22(c), 22(d) or 22(e), the date on which the loss is sustained, the damage is done, or the injurious affection occurs, as the case may be;

(c)in the case of compensation payable under paragraph 25(6), the date on which the expenses become payable.

(3) If it appears to a person that he may become liable to pay to another compensation under this Schedule or interest under this paragraph he may, if the other person requests him in writing to do so, make one or more payments on account of such compensation or interest.

(4) If, after a payment has been made by a person under sub-paragraph (3)—

(a)it is agreed or determined that he is not liable to pay compensation or interest; or

(b)by reason of any agreement or determination, a payment under that sub-paragraph is shown to be excessive,

the payment or excess, as the case may be, is recoverable by that person.

(2)

1961 c. 33. Section 5 was amended by the Planning and Compensation Act 1991 (c. 34), sections 70 and 84, and Schedules 15 and 19.

(3)

Section 2 was amended by the Local Government, Planning and Land Act 1980 (c. 65), section 193 and Schedule 33.

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill