[F1SCHEDULE 9AE+WSpecies control agreements and orders (England and Wales)

Textual Amendments

PART 3E+WSpecies control orders

EnforcementE+W

18(1)This paragraph applies where an environmental authority considers that an owner of premises required by a species control order to carry out a species control operation has not done so by the date or in the way specified in the order.E+W

(2)The authority must give the owner notice to that effect.

(3)Sub-paragraphs (4) to (6) apply if, after a week after giving notice under sub-paragraph (2), the authority considers that the owner has still not carried out the species control operation in the way specified in the order.

(4)The authority may carry out the operation itself or carry out such further work as is necessary to ensure that the operation is carried out in the way specified in the order.

(5)The authority may recover from the owner any expenses reasonably incurred by it in doing so (less any payment which the authority would apart from this paragraph have been required to make to the owner in respect of the carrying out of the operations by the owner).

(6)The authority is not required to make any payment provided for under paragraph 13(2)(b) in relation to the operation (and may recover any payment made under that paragraph).]