The Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2017

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol).

Request for scoping opinions

This adran has no associated Nodiadau Polisi

12.—(1) A developer may request the Scottish Ministers to adopt a scoping opinion.

(2) A request under paragraph (1) must include—

(a)a description of the location of the development, including a plan sufficient to identify the land;

(b)a brief description of the nature and purpose of the development and of its likely significant effects on the environment; and

(c)such other information or representations as the developer may wish to provide or make.

(3) If the Scottish Ministers consider that they have not been provided with sufficient information, they must, within three weeks of receipt of the request under paragraph (1), notify the developer of the points on which they require further information.

(4) The Scottish Ministers must not adopt a scoping opinion in response to a request under paragraph (1) until they have consulted—

(a)the consultation bodies; and

(b)any other public body which the Scottish Ministers consider is likely to have an interest in the proposed development by reason of that body’s specific environmental responsibilities or local and regional competencies.

(5) The Scottish Ministers when adopting a scoping opinion must take into account—

(a)the information provided by the developer, in particular information provided by the developer in respect of the specific characteristics of the development, including its location and technical capacity and its likely impact on the environment; and

(b)any representations made to them in response to consultation undertaken in accordance with paragraph (4).

(6) The Scottish Ministers must, within the period of 9 weeks beginning with the date of receipt of a request or such longer period as they may reasonably require, adopt a scoping opinion and send a copy of the scoping opinion to the developer and to the planning authority.

(7) The adoption of a scoping opinion by the Scottish Ministers does not preclude the Scottish Ministers from requiring of the developer information in connection with any EIA report submitted in connection with an application for Electricity Act consent for the same development as referred to in the scoping opinion.

(8) Where the developer has, at the same time as making a request for a screening opinion under regulation 8(1), made a request under paragraph (1), and the Scottish Ministers have adopted a screening opinion to the effect that the development is EIA development, the Scottish Ministers are to begin the procedures relating to scoping on the date on which they give the screening opinion.

(9) The Scottish Ministers may at their own volition adopt a scoping opinion and paragraphs (4), (5) and (7) apply in relation to such a scoping opinion as they apply where a request is made under paragraph (1).

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Policy Note

Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill