Duration of planning permission

35Duration of planning permission: general

(1)Section 91 of TCPA 1990 (general condition limiting duration of planning permission) is amended in accordance with subsections (2) to (6).

(2)In subsection (1), in paragraph (a), for the words before “beginning with” substitute “the applicable period,”.

(3)In subsection (3)—

(a)after “shall” insert “(subject to subsections (3ZA) and (3ZB))”;

(b)for the words from “expiration of” to the end, substitute “expiration of the applicable period, beginning with the date of the grant”.

(4)After subsection (3) insert—

(3ZA)Subsection (3ZB) applies if—

(a)a section 73 permission is granted for the development of land in Wales, but without the condition required by subsection (1), and

(b)the previous permission was granted, or deemed to have been granted (whether by virtue of this section or otherwise) subject to a condition as to the time within which development was to be begun.

(3ZB)The section 73 permission shall be deemed to have been granted subject to the condition that the development to which it relates must be begun not later than the date on or before which the previous permission required development to be begun.

(3ZC)The previous permission, in relation to a section 73 permission, is the previous planning permission referred to in section 73(1).

(3ZD)References in subsections (3ZA) to (3ZC) to a section 73 permission are to a planning permission granted under section 73.

(5)In subsection (3A), after “validity” insert “, in respect of the development of land in England,”.

(6)After subsection (4) insert—

(5)The applicable period—

(a)in relation to England, is three years;

(b)in relation to Wales, is five years.

(7)In section 73 of TCPA 1990 (determination of applications to develop land without compliance with conditions previously attached), in subsection (5), after “under this section” insert “for the development of land in England”.

(8)In section 51 of PCPA 2004 (duration of permission and consent), in subsection (1), omit paragraph (a).

36Duration of outline planning permission

(1)Section 92 of TCPA 1990 (outline planning permission) is amended in accordance with subsections (2) to (6).

(2)In subsection (2), for paragraph (b) substitute—

(b)that, in the case of outline planning permission for the development of land in England, the development to which the permission relates must be begun not later than the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved;

(c)that, in the case of outline planning permission for the development of land in Wales, the development must be begun no later than—

(i)the expiration of five years from the date of the grant of outline planning permission, or

(ii)if later, the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved.

(3)In subsection (3), after “shall” insert “(subject to subsections (3A) to (3D))”.

(4)After subsection (3) insert—

(3A)If outline planning permission is granted under section 73 for the development of land in Wales, but without the condition required by subsection (2)(a), it shall be deemed to have been granted subject to the following condition.

(3B)The condition is that, in the case of any reserved matter, application for approval must be made not later than the date on or before which the previous permission required application for approval, in the case of any matter reserved under the previous permission, to be made.

(3C)If outline planning permission is granted under section 73 for the development of land in Wales, but without a condition required by subsection (2)(c), it shall be deemed to have been granted subject to the following condition.

(3D)The condition is that the development to which the permission relates must be begun not later than the date on or before which the previous permission required development to be begun.

(3E)The previous permission, in relation to outline planning permission granted under section 73, is the previous planning permission referred to in subsection (1) of that section.

(5)In subsection (4), omit the words from “of three” to “two years”.

(6)In subsection (5), after “(b)” insert “or (c)”.

(7)In section 51 of PCPA 2004 (duration of permission and consent), omit subsection (2).

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open y Ddeddf Gyfan

Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’. Dim ond yn Saesneg y mae’r fersiwn ddiwygiedig ar gael ar hyn o bryd.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed) - Saesneg: Mae'r wreiddiol Saesneg fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed)-Cymraeg:Y fersiwn Gymraeg wreiddiol o’r ddeddfwriaeth fel yr oedd yn sefyll pan gafodd ei deddfu neu ei gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Dangos Nodiadau Eglurhaol ar gyfer Adrannau: Yn arddangos rhannau perthnasol o’r nodiadau esboniadol wedi eu cydblethu â chynnwys y ddeddfwriaeth.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Nodiadau Esboniadol

Text created by the Welsh Government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes accompany all Acts of the National Assembly for Wales.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill