Reservoirs (Scotland) Act 2011

36Safety reports: compliance

This section has no associated Explanatory Notes

(1)The reservoir manager of a controlled reservoir must (subject to section 59(3)) comply with any direction in a safety report issued to the manager.

(2)The construction engineer must, not later than 28 days after being satisfied that each measure directed in the safety report has been taken, give the reservoir manager a safety measure certificate.

(3)A safety measure certificate must specify—

(a)the safety report to which it relates,

(b)the measure taken,

(c)any measure that has yet to be taken.

(4)A construction engineer must, not later than 28 days after giving a safety measure certificate under subsection (2), give SEPA a copy of it.