New section 9F – Effect of scheduled monument consent on scheduled monument enforcement notice
26.Section 9F applies where a scheduled monument enforcement notice has been issued, and scheduled monument consent is then granted under new section 2(3A) of the 1979 Act (inserted by section 2 of the Act) for the retention of works or of works which do not comply with a condition in the original scheduled monument consent. In such cases, the notice ceases to have effect in so far as it requires the works to cease, steps to be taken involving the works not being retained or compliance with that condition.