xmlns:atom="http://www.w3.org/2005/Atom"

Part 3Flood risk assessment, maps and plans

Local flood risk management plans

37Local flood risk management plans: interim report

(1)Not earlier than 2 years and not later than 3 years after a local flood risk management plan is finalised, the lead authority must—

(a)review the plan, and

(b)publish a report on the conclusions of the review including information on the progress that has been made towards implementing the measures identified in the implementation part of the plan.

(2)The lead authority must make copies of the report available for public inspection.