xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

Part 3SFlood risk assessment, maps and plans

Flood hazard maps and flood risk mapsS

21SEPA to prepare flood hazard maps and flood risk mapsS

(1)SEPA must prepare flood hazard maps and flood risk maps in accordance with this section and sections 22 and 23.

(2)Flood hazard maps and flood risk maps must be prepared—

(a)by 22nd December 2013,

(b)for the potentially vulnerable areas in each flood risk management district,

(c)at the appropriate scale, and

(d)so as to secure that the maps for the district (taken together) cover all such areas.

Commencement Information

I1S. 21 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.